BLD10-00254
| BLD-Energy code compliance | 3/22/2010 | 3/22/2010 | 3/22/2010 5:28:55 PM | P | PASS |
|
|
larry Phone #: ###-####
|
BLD10-00253
| BLD-Energy code compliance | 3/22/2010 | 3/22/2010 | 3/22/2010 5:27:42 PM | P | PASS |
|
|
larry Phone #: ###-####
|
BLD10-00239
| BLD-Energy code compliance | 3/22/2010 | 3/22/2010 | 3/22/2010 4:57:22 PM | P | PASS |
|
|
larry Phone #: ###-####
|
BLD09-00945
| BLD-Other | 3/22/2010 | 3/22/2010 | 3/22/2010 4:47:54 PM | P | PASS |
|
|
Please call 1/2 hour prior upon arrival, thanks. Inspection requested from web by: Darren Gossett Phone #: ###-#### Ceiling grid select area.
|
BLD10-00179
| BLD-Framing/Rough-in | 3/22/2010 | 3/22/2010 | 3/22/2010 2:23:59 PM | A | PASS |
|
|
Firewall construction Inspection requested from web by: James Larkin Phone #: ###-#### WIP Partial on Firewall....OK
|
BLD10-00178
| BLD-Framing/Rough-in | 3/22/2010 | 3/22/2010 | 3/22/2010 1:26:02 PM | A | PART |
|
|
Firewall construction Inspection requested from web by: James Larkin Phone #: ###-#### WIP Firewall OK so far.
|
BLD10-00330
| BLD-Final | 3/19/2010 | 3/22/2010 | 3/22/2010 1:07:20 PM | A | PASS |
|
|
dan Phone #: ###-#### C/C issued
|
BLD10-00330
| DOC - Permit Finaled | 3/22/2010 | 3/22/2010 | 3/22/2010 1:06:28 PM | P | PASS |
|
|
|
BLD10-00177
| BLD-Framing/Rough-in | 3/22/2010 | 3/22/2010 | 3/22/2010 12:49:25 PM | A | PART |
|
|
Firewall construction Inspection requested from web by: James Larkin Phone #: ###-#### WIP.....Fire wall OK so far.
|
BLD10-00176
| BLD-Framing/Rough-in | 3/22/2010 | 3/22/2010 | 3/22/2010 10:57:03 AM | A | PART |
|
|
Firewall construction Inspection requested from web by: James Larkin Phone #: ###-#### WIP Fire wall OK so far.....
|