ELE15-03396
| Permanent Service | 3/22/2016 | 3/22/2016 | 3/22/2016 3:58:20 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Needed rough in inspection
|
ELE15-03396
| Electrical Rough-In | 3/22/2016 | 3/22/2016 | 3/22/2016 2:26:10 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Rough in for transformer. Grounding electrode system off building steel. Rough in ok
|
ELE16-00893
| Electrical Rough-In | 3/22/2016 | 3/22/2016 | 3/22/2016 2:23:08 PM | P | PASS |
|
|
Inspect soffit wiring for cover. Phone #: ###-#### Inspection requested via web by Robert Schroder Soffits rough in ok cover
|
ELE16-00809
| Electrical Rough-In | 3/22/2016 | 3/22/2016 | 3/22/2016 1:23:56 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kevin Burke Bathrooms walls and hardlids rough in ok cover
|
ELE16-00901
| Electrical Rough-In | 3/22/2016 | 3/22/2016 | 3/22/2016 12:35:54 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Work room and break room to be done later. CT-3 wall and hard soffit rough in ok cover
|
ELE16-00727
| Electrical Rough-In | 3/21/2016 | 3/22/2016 | 3/22/2016 12:14:06 PM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Wrong address requested.
|
ELE16-00147
| Temporary Service | 3/21/2016 | 3/22/2016 | 3/22/2016 10:41:04 AM | A | CANC |
|
|
Michael// please call before Phone #: ###-#### Needed conference.
|
ELE16-00147
| Conference | 3/22/2016 | 3/22/2016 | 3/22/2016 10:25:44 AM | P | DONE |
|
|
Michael// please call before Phone #: ###-#### Discussed temp pole requirements. Pole laying on ground, GFCI receptacles installed for construction, GFCI installed for 120 volt RV receptacle. Informed how deep to set pole and max height of overcurrent device handles. Shall set pole and drive ground rod prior to inspection for temp power.
|
ELE16-00881
| Electrical Rough-In | 3/21/2016 | 3/22/2016 | 3/22/2016 10:03:45 AM | A | PASS |
|
|
We are requesting a electrical service inspection for the Bldg. 2 UPS panel for tomorrow 3/22/16 in the AM. Our contact is Rich ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Feed from building 4 electrical room to UPS system for server room in building 2. Both breaker and panel shall be identified clearly where originate and terminate from. Rough in ok cover.
|
ELE16-00505
| Final | 3/21/2016 | 3/22/2016 | 3/22/2016 9:10:43 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by ron spen cer Final ok
|
ELE16-00884
| Temporary Service | 3/21/2016 | 3/22/2016 | 3/22/2016 8:45:37 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Bob Glenn t/s u/g n ok
|
ELE16-00885
| Temporary Service | 3/21/2016 | 3/22/2016 | 3/22/2016 8:22:16 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Bob Glenn t/s u/g n ok
|