Inspections for the day of: Tuesday, March 22, 2016.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE15-03396 Permanent Service3/22/20163/22/20163/22/2016 3:58:20 PMPPASS
Phone #: ###-#### Inspection requested via web by Stacie Tasker
Needed rough in inspection
ELE15-03396 Electrical Rough-In3/22/20163/22/20163/22/2016 2:26:10 PMPPASS
Phone #: ###-#### Inspection requested via web by Stacie Tasker
Rough in for transformer. Grounding electrode system off building steel. Rough in ok
ELE16-00893 Electrical Rough-In3/22/20163/22/20163/22/2016 2:23:08 PMPPASS
Inspect soffit wiring for cover. Phone #: ###-#### Inspection requested via web by Robert Schroder
Soffits rough in ok cover
ELE16-00809 Electrical Rough-In3/22/20163/22/20163/22/2016 1:23:56 PMPPASS
Phone #: ###-#### Inspection requested via web by Kevin Burke
Bathrooms walls and hardlids rough in ok cover
ELE16-00901 Electrical Rough-In3/22/20163/22/20163/22/2016 12:35:54 PMPPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton
Work room and break room to be done later. CT-3 wall and hard soffit rough in ok cover
ELE16-00727 Electrical Rough-In3/21/20163/22/20163/22/2016 12:14:06 PMACANC
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Wrong address requested.
ELE16-00147 Temporary Service3/21/20163/22/20163/22/2016 10:41:04 AMACANC
Michael// please call before Phone #: ###-#### Needed conference.
ELE16-00147 Conference3/22/20163/22/20163/22/2016 10:25:44 AMPDONE
Michael// please call before Phone #: ###-#### Discussed temp pole requirements. Pole laying on ground, GFCI receptacles installed for construction, GFCI installed for 120 volt RV receptacle. Informed how deep to set pole and max height of overcurrent device handles. Shall set pole and drive ground rod prior to inspection for temp power.
ELE16-00881 Electrical Rough-In3/21/20163/22/20163/22/2016 10:03:45 AMAPASS
We are requesting a electrical service inspection for the Bldg. 2 UPS panel for tomorrow 3/22/16 in the AM. Our contact is Rich ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Feed from building 4 electrical room to UPS system for server room in building 2. Both breaker and panel shall be identified clearly where originate and terminate from. Rough in ok cover.
ELE16-00505 Final3/21/20163/22/20163/22/2016 9:10:43 AMAPASS
Phone #: ###-#### Inspection requested via web by ron spen cer
Final ok
ELE16-00884 Temporary Service3/21/20163/22/20163/22/2016 8:45:37 AMAPASS
Phone #: ###-#### Inspection requested via web by Bob Glenn
t/s u/g n ok
ELE16-00885 Temporary Service3/21/20163/22/20163/22/2016 8:22:16 AMAPASS
Phone #: ###-#### Inspection requested via web by Bob Glenn
t/s u/g n ok