Inspections for the day of: Tuesday, March 22, 2016.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00822 INSP-Sprinkler Rough-in/Hydro3/21/20163/22/20163/22/2016 2:02:26 PMPPART
Underground hydro test passed. Overhead rough-in failed due to the approved plans not matching the installation such as riser nipples installed where none are shown. Also missing branch line restraints. Plan modifications are required showing all piping changes and the additional fittings in the mains and branchlines.
BLD16-00298 FIRE-Final Inspection3/22/20163/22/20163/22/2016 1:16:11 PMPPASS
Life safety passed. I noted single row racks but they did not measure over 8' vertical and the storage was under 12' at the time of inspection.
NAF15-00043 INSP-Sprinkler Rough-in3/21/20163/22/20163/22/2016 11:39:39 AMPFAIL
Plan modifications needed due to extensive changes needed such as adding upright sprinkler coverage that is missing is some locations and additional fittings have been added in the mains and riser nipples.
BLD16-00477 FIRE-Final Inspection3/21/20163/22/20163/22/2016 8:19:24 AMAPASS
life safety passed