ELE18-01001
| Final | 3/22/2018 | 3/22/2018 | 3/22/2018 2:54:19 PM | P | PASS |
|
|
New LED canopy fixtures Phone #: ###-#### Inspection requested via web by Paul White...job complete...ok to final
|
ELE18-01001
| Electrical Rough-In | 3/22/2018 | 3/22/2018 | 3/22/2018 2:53:52 PM | P | PASS |
|
|
New LED canopy fixtures Phone #: ###-#### Inspection requested via web by Paul White...new lights...verified UL listing and how wired by pictures sent of fixture paperwork and images of top of canopy..ok
|
ELE18-00366
| Electrical Rough-In | 3/21/2018 | 3/22/2018 | 3/22/2018 1:50:56 PM | P | PASS |
|
|
Ceiling Cover. Von is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen...grid ok to cover
|
ELE12-01902
| ELE-Aging Inspection | 3/22/2018 | 3/22/2018 | 3/22/2018 11:53:27 AM | | FAIL |
|
|
contractor making no attempt
|
ELE12-01900
| ELE-Aging Inspection | 3/22/2018 | 3/22/2018 | 3/22/2018 11:53:01 AM | | FAIL |
|
|
contractor making no attempt
|
ELE14-00081
| Final | 3/22/2018 | 3/22/2018 | 3/22/2018 11:51:58 AM | P | PASS |
|
|
ok to final
|
ELE14-00081
| Electrical Rough-In | 3/22/2018 | 3/22/2018 | 3/22/2018 11:51:40 AM | P | PASS |
|
|
UL listings verified and disconnects
|
ELE14-00070
| Final | 3/22/2018 | 3/22/2018 | 3/22/2018 11:42:43 AM | P | PASS |
|
|
job complete...ok to final
|
ELE18-00985
| Electrical Rough-In | 3/22/2018 | 3/22/2018 | 3/22/2018 11:40:13 AM | P | PASS |
|
|
rough in...discussed with contractor ok to cover all walls...needed additions and issues needing to be addressed will be done before final
|
ELE17-04183
| Final | 3/20/2018 | 3/22/2018 | 3/22/2018 11:17:34 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Steve VanWinkle...ok to final
|
ELE18-00408
| Electrical Rough-In | 3/21/2018 | 3/22/2018 | 3/22/2018 10:20:55 AM | A | FAIL |
|
|
We need a wall cover inspection. Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...no access...reported black mold in work area ceiling...treatment of black mold has been performed...proper safety equipment shall be supplied and required to enter site and do inspection
|
ELE18-00365
| Final | 3/21/2018 | 3/22/2018 | 3/22/2018 10:09:50 AM | A | PASS |
|
|
garage code 8888 Phone #: ###-#### Inspection requested via web by kevin blackmon..ok to final
|
ELE18-00120
| Final | 3/21/2018 | 3/22/2018 | 3/22/2018 9:49:28 AM | A | NR |
|
|
We are requesting a final inspection for the dressing room area, walls and ceiling. Contact is Larry Looney ###-#### or on-site is Curtis Burney with ESI, ###-#### Phone #: ###-#### Inspection requested via web by Larry Looney...walls are not complete...added rough for ceiling grid of dressing rooms
|
ELE18-00120
| Electrical Rough-In | 3/22/2018 | 3/22/2018 | 3/22/2018 9:48:11 AM | A | PASS |
|
|
Contact is Larry Looney ###-#### or on-site is Curtis Burney with ESI, ###-#### Phone #: ###-#### Inspection requested via web by Larry Looney....ceiling grid for dressing rms ok
|
ELE18-00690
| Final | 3/21/2018 | 3/22/2018 | 3/22/2018 9:21:40 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ryan Wake...ok to final
|
ELE18-00829
| Final | 3/21/2018 | 3/22/2018 | 3/22/2018 8:27:02 AM | A | PASS |
|
|
Any questions let me know. Thank you. Phone #: ###-#### Inspection requested via web by David Kubik...ok to final
|
ELE18-00828
| Final | 3/21/2018 | 3/22/2018 | 3/22/2018 8:26:31 AM | A | PASS |
|
|
It''s in. Phone #: ###-#### Inspection requested via web by David Kubik...ok to final
|
ELE18-00349
| Final | 3/20/2018 | 3/22/2018 | 3/21/2018 12:48:12 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Steve VanWinkle...verified..ok to final
|