BLD05-03176
| FIRE-Final Inspection | 3/22/2006 | 3/23/2006 | 3/23/2006 3:03:38 PM | A | PASS |
|
|
Project related alarm and sprinkler permits have been completed. Fire life safety inspection passed, corrections complete.
|
FIR06-00037
| INSP-Final Inspection | 3/23/2006 | 3/23/2006 | 3/23/2006 3:00:30 PM | P | PASS |
|
|
Required corrections have been made, fire sprinkler permit finaled.
|
FIR05-00575
| INSP-Final Inspection | 3/23/2006 | 3/23/2006 | 3/23/2006 2:51:17 PM | P | PASS |
|
|
Fire alarm passed final inspection.
|
FIR06-00073
| INSP-Supply line flush | 3/21/2006 | 3/23/2006 | 3/23/2006 2:43:24 PM | P | PART |
|
|
UG fire supply line has been relocated to attain the proper depth of bury as required, thrust blocking verified, UG is okay to cover.
|
BLD04-00944
| FIRE-Final Inspection | 3/22/2006 | 3/23/2006 | 3/23/2006 11:11:08 AM | A | FAIL |
|
|
Fire lane marking is not complete, provide egress illumination at the third and second floor lobby areas, mount fire extinguishers with current tags as discussed, door hardware is missing at the riser room, remove SD covers at all locations and tape and paper at the sprinkler heads in the garages prior to final inspection, provide keys for the knox box.
|
FIR05-00270
| FIR-Aging Inspection | 3/23/2006 | 3/23/2006 | 3/23/2006 10:13:53 AM | | DEFR |
|
|
Work in progress.
|
FIR06-00177
| INSP-Sprinkler Rough-in/Hydro | 3/22/2006 | 3/23/2006 | 3/23/2006 9:44:09 AM | A | PART |
|
|
Overhead rough-in is good for cover at the drop ceiling areas, final pending ceiling tile and escutcheons at all locations.
|