Inspections for the day of: Monday, March 23, 2009.
Number of inspections: 3
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00035 Conference3/9/20093/23/20093/23/2009 3:27:49 PMPPASS
2:30pm: Reviewed site with Strata, (Brightons consultant) and C. Smith. Reminder that site stabilization is a federal requirement.upon completion of activities, including de-watering basin and channels.
ESC07-01438 BMP Violation3/20/20093/23/20093/23/2009 10:52:43 AMAPART
Follow up: Inserts in place, rock entrance in place. Verbal to RP that additional rock is needed prior to forecasted rain from ashalt to start of existing rock, appr. 8 feet, if not this low area will become very muddy and cause trackout issues. Will follow up
ESC08-00183 General Inspection3/23/20093/23/20093/23/2009 10:21:08 AMAPART
Site looks good, verbal to Habitat that sediment barrier around irrigation drops are in need of better securing to post. Tom Wood-###-#### will make the necessary maintanence today. Also talked to Dennis ###-####.