Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-03640 BLD-Framing/Rough-in3/23/20003/24/20003/24/2000 12:00:00 AMANR
Ernie ###-#### ernie to set up meetting with k.p. penicial engineers to resolve design change to get shop drawings to have phi jacks of mti special insp. and city approval plan.. 3/24/00 12:17:43 PM
BLD00-00276 BLD-Footing3/23/20003/24/20003/24/2000 12:00:00 AMAPART
mitch ###-#### work in progess rebar that is placed is ok pending report from special inspection. 3/24/00 8:49:57 AM
BLD00-00258 BLD-Framing/Rough-in3/23/20003/24/20003/24/2000 12:00:00 AMAPASS
ken ###-####
BLD00-00258 BLD-Framing/Rough-in3/23/20003/24/20003/24/2000 12:00:00 AMAPASS
ken ###-####
BLD99-01720 BLD-Framing/Rough-in3/24/20003/24/20003/24/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 03/24/2000 at 07:21:10. Contact: ###-####.fire stopping of floor system at prerock areas at drop locations ok. 3/24/00 10:40:04 AM
BLD00-00239 BLD-Framing/Rough-in3/24/20003/24/20003/24/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 03/24/2000 at 08:25:36. Contact: . work covered w/o approval all trades floor patch placed w/o inap rated sys. 3/24/00 4:47:18 PM
BLD00-00468 BLD-Framing/Rough-in3/24/20003/24/20003/24/2000 12:00:00 AMPPART
###-####
BLD99-02180 BLD-Final3/23/20003/24/20003/24/2000 12:00:00 AMPPART
Dan ###-#### ada signage at restarooms , pending other sign offs. temp occ ok 3/24/00 2:50:08 PM
BLD00-00298 BLD-Framing/Rough-in3/23/20003/24/20003/24/2000 12:00:00 AMPPART
###-#### ken ###-####
BLD00-00298 BLD-Energy code compliance3/23/20003/24/20003/24/2000 12:00:00 AMPPASS