FIR05-00239
| INSP-Sprinkler Rough-in/Hydro | 3/23/2006 | 3/24/2006 | 3/24/2006 6:33:55 PM | P | CANC |
|
|
UG hydro test canceled by contractor, not ready for inspection.
|
FIR05-00594
| INSP-Sprinkler Rough-in | 3/23/2006 | 3/24/2006 | 3/24/2006 6:31:53 PM | P | PART |
|
|
Begin 72hr test of the water level at the underground storage tanks.
|
FIR05-00542
| INSP-Final Inspection | 3/23/2006 | 3/24/2006 | 3/24/2006 2:43:34 PM | P | FAIL |
|
|
Need to complete c/n items, perform forward flow, certify backflow preventer, provide mfg. data sheet for the expansion tank listing for fire protection service, test related alarms.
|
FIR05-00898
| INSP-Final Inspection | 3/23/2006 | 3/24/2006 | 3/24/2006 2:40:07 PM | P | FAIL |
|
|
Two tamper switches at the main control valves are not functional, panel for the local haz mat alarm has no phone line, need to provide completed NFPA 72 inspection and testing form prior to final inspection, no further inspection done at this time.
|
FIR05-00542
| INSP-Sprinkler Rough-in/Hydro | 3/23/2006 | 3/24/2006 | 3/24/2006 2:33:21 PM | A | PART |
|
|
Overhead hydrostatic test for the wet and antifreeze systems is satisfactory, one row of heads in the charging room is too low, need to certifiy the backflow, perform forward flow test.
|
BLD05-01577
| FIRE-Final Inspection | 3/23/2006 | 3/24/2006 | 3/24/2006 11:39:48 AM | A | FAIL |
|
|
The entrance gates are not installed at this time for verification of required width, functionality, hardware, etc, need to provide an additional building address facing Gekeler street.
|
BLD06-00367
| FIRE-Final Inspection | 3/23/2006 | 3/24/2006 | 3/24/2006 10:12:29 AM | A | FAIL |
|
|
Door hardware at some locations is not installed, need to mount fire extinguishers, the project related fire alarm permit must be issued, installed, inspected and approved (this includes the access controlled egress doors interconnection) prior to life safety final.
|