FIR14-00277
| INSP-Final Inspection | 3/23/2015 | 3/24/2015 | 3/25/2015 5:09:07 PM | P | PASS |
|
|
UG fire supply line permit final approved.
|
BLD15-00350
| FIRE-Final Inspection | 3/24/2015 | 3/24/2015 | 3/24/2015 2:06:24 PM | P | PASS |
|
|
Fire life safety inspection completed satisfactory.
|
FIR15-00167
| INSP-Final Inspection | 3/24/2015 | 3/24/2015 | 3/24/2015 2:05:25 PM | P | PASS |
|
|
Fire sprinkler permit final approved.
|
FIR15-00167
| INSP-Sprinkler Rough-in | 3/24/2015 | 3/24/2015 | 3/24/2015 2:03:46 PM | P | PASS |
|
|
Fire sprinkler permit work okay for final after mixed temp heads replaced with matched while on site.
|
FIR14-00437
| INSP-Sprinkler Rough-in/Hydro | 3/23/2015 | 3/24/2015 | 3/24/2015 12:41:57 PM | A | PART |
|
|
Completed satisfactory hydrostatic test of the new dry system piping.
|
FIR14-00867
| INSP-Sprinkler Rough-in/Hydro | 3/23/2015 | 3/24/2015 | 3/24/2015 12:39:41 PM | A | PART |
|
|
Completed overhead inspection for both the first and second floor systems. Rough-in passed.
|
FIR15-00087
| INSP-Final Inspection | 3/23/2015 | 3/24/2015 | 3/24/2015 10:54:30 AM | A | PART |
|
|
Inspection for overhead rough-in completed at the grid ceiling areas. Need to relocate one new pendent head at the NW corner office.
|
BLD14-03402
| FIRE-Final Inspection | 3/23/2015 | 3/24/2015 | 3/24/2015 10:38:54 AM | A | PASS |
|
|
Verified noted correction items for completion. Life safety passed.
|