Inspections for the day of: Monday, March 25, 2002.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD02-00429 BLD-Foundation3/22/20023/25/20023/25/2002 12:00:00 AMAPASS
bob--###-#### found
BLD01-02607 BLD-Conference3/22/20023/25/20023/25/2002 12:00:00 AMANR
Scheduled by Inspector: 415 On 3/22/2002 2:13:41 PM wants to see carl, adding office space, will need sprinkler modification, etc. unable to contact, rescheduled 3/25/2002 11:40:22 AM
BLD01-01993 BLD-Conference3/22/20023/25/20023/25/2002 12:00:00 AMAPASS
###-#### phase 2 stair rail upgrade ok. 3/25/2002 11:11:09 AM
BLD01-00594 BLD-Final3/23/20023/25/20023/25/2002 12:00:00 AMANR
Scheduled by a contractor via Hello! on 03/23/2002 at 12:52:53. Contact: ###-####. keep c/n ...install handrails per c/n 3/25/2002 10:34:11 AM
BLD01-00603 BLD-Final3/23/20023/25/20023/25/2002 12:00:00 AMANR
Scheduled by a contractor via Hello! on 03/23/2002 at 12:54:55. Contact: ###-####...keep c/n re rails 3/25/2002 10:34:32 AM
BLD01-00595 BLD-Final3/23/20023/25/20023/25/2002 12:00:00 AMANR
Scheduled by a contractor via Hello! on 03/23/2002 at 12:56:45. Contact: ###-####. keep c/n re handrails 3/25/2002 10:34:44 AM
BLD01-02607 BLD-Conference3/25/20023/25/20023/25/2002 12:00:00 AMPFAIL
Scheduled by Inspector: 340 On 3/25/2002 11:16:13 AM c/n...install guardrail at added man-door at roof-top mech. room; also submit add'l cert of value for add'l proposed elec & finish work within bldg... 3/25/2002 4:27:57 PM
BLD01-00603 BLD-Final3/25/20023/25/20023/25/2002 12:00:00 AMPPART
Scheduled by Inspector: 340 On 3/25/2002 11:37:09 AM ; keep c/n , ok for t/o. 3/25/2002 3:24:06 PM
BLD01-00604 BLD-Conference3/25/20023/25/20023/25/2002 12:00:00 AMPPASS
Scheduled by Inspector: 340 On 3/25/2002 11:38:03 AM re handrails, install extensions, & add'l rails as needed 3/25/2002 3:25:02 PM
BLD01-00604 BLD-Final3/25/20023/25/20023/25/2002 12:00:00 AMPPART
Scheduled by Inspector: 340 On 3/25/2002 11:38:31 AM keep c/n, ok for t/o. 3/25/2002 3:25:32 PM
BLD01-00594 BLD-Final3/25/20023/25/20023/25/2002 12:00:00 AMPPART
Scheduled by Inspector: 340 On 3/25/2002 11:39:34 AM keep c/n ok for t/o 3/25/2002 3:15:27 PM
BLD01-00594 BLD-Conference3/25/20023/25/20023/25/2002 12:00:00 AMPPASS
Scheduled by Inspector: 340 On 3/25/2002 11:36:16 AM w/ handrail fabricator: install extensions 3/25/2002 3:13:57 PM
BLD01-000-1 BLD-Conference3/25/20023/25/20023/25/2002 12:00:00 AMPPASS
Scheduled by Inspector: 340 On 3/25/2002 3:28:41 PM w/ bldr re finals, need fire 1st. 3/25/2002 4:43:34 PM