Inspections for the day of: Thursday, March 25, 2010.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD09-02252 BLD-Aging Inspection3/25/20103/25/20103/25/2010 4:41:18 PM NR
BLD10-00183 BLD-Framing/Rough-in3/25/20103/25/20103/25/2010 4:40:13 PMPPASS
Base and face layer of 5/8 type x rock for 2hr. firewall, one side only, 2nd. floor.
BLD10-00182 BLD-Framing/Rough-in3/25/20103/25/20103/25/2010 4:39:22 PMPPASS
Base and face layers for 2hr. firewall, 2nd. floor , one side only.
BLD10-00181 BLD-Framing/Rough-in3/25/20103/25/20103/25/2010 4:37:42 PMPPASS
base and face layer for 2hr. firewall, remaining side, 2nd. floor.
BLD10-00516 BLD-Final3/25/20103/25/20103/25/2010 2:54:11 PMPPASS
Robert Phone #: ###-####. ok for perm occ.
BLD09-02286 BLD-Final3/24/20103/25/20103/25/2010 2:12:53 PMPPASS
Tim Phone #: ###-####. Ok for perm occ. Restroom corridor issue was resolved.
BLD09-02287 BLD-Final3/24/20103/25/20103/25/2010 2:11:15 PMPPASS
Tim Phone #: ###-####
BLD09-02287 DOC - Permit Finaled3/25/20103/25/20103/25/2010 2:11:07 PMPPASS
Letter of completion was issued. Wires to diifusers were installed.
BLD10-00011 BLD-Final3/24/20103/25/20103/25/2010 10:17:55 AMAPASS
please call for onsite visit. Inspection requested from web by: Scott Zierler Phone #: ###-####
BLD10-00011 DOC - Permit Finaled3/25/20103/25/20103/25/2010 10:17:45 AMPPASS
Certificate of occupancy issued. Noted that this unit only needed minor interior finish work to complete.
ESC05-01660 Site Final3/25/20103/25/20103/25/2010 10:16:46 AMAPASS
ESC05-01660 DOC - Permit Finaled3/25/20103/25/20103/25/2010 10:16:39 AMPPASS
Final stabalization has been completed.