Inspections for the day of: Wednesday, March 25, 2015.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00618 INSP-Sprinkler Rough-in3/25/20153/25/20153/25/2015 3:24:17 PMPPASS
Tenting passed. Piping can be covered.
FIR15-00124 INSP-Sprinkler Rough-in/Hydro3/25/20153/25/20153/25/2015 3:10:33 PMPFAIL
Left message on contacts voice mail that I was on the way. Don called when I was on site and let me know that the technition could not make it and he would reschule
FIR14-00910 INSP-Sprinkler Rough-in/Hydro3/24/20153/25/20153/25/2015 3:04:00 PMAPASS
Overhead hydro and rough-in passed
FIR15-00130 INSP-Sprinkler Rough-in3/24/20153/25/20153/25/2015 2:22:25 PMAPASS
Pharmacy piping is ok to re-cover.
FIR15-00105 INSP-Sprinkler Rough-in/Hydro3/24/20153/25/20153/25/2015 2:07:36 PMAPASS
Hydro test fo the fire pump assmbly passed
BLD14-01496 FIRE-Final Inspection3/25/20153/25/20153/25/2015 12:45:30 PMPPASS
Life safety passed
FIR14-00569 INSP-Final Inspection3/25/20153/25/20153/25/2015 11:30:56 AMPPASS
Permit finaled
BLD15-00358 FIRE-Final Inspection3/24/20153/25/20153/25/2015 11:30:42 AMAPASS
Life safety passed. Fire alarm contractor and electrical contractor are currently repairing portions of the mall fire alarm system. I spoke to Ray Criner about follow up inspections to verifiy that the entire mall system gets repaired and becomes 100% functional.
BLD14-02997 FIRE-Final Inspection3/24/20153/25/20153/25/2015 9:48:16 AMAPASS
Life safety passed
FIR14-00848 INSP-Final Inspection3/24/20153/25/20153/25/2015 9:06:14 AMAPASS
Permit finaled
FIR14-00602 INSP-Final Inspection3/24/20153/25/20153/25/2015 9:03:38 AMAPASS
Permit finaled
FIR14-00722 INSP-Final Inspection3/24/20153/25/20153/25/2015 9:01:05 AMAPASS
Permit finaled
FIR15-00158 INSP-Final Inspection3/24/20153/25/20153/25/2015 8:59:49 AMAPASS
Permit finaled