BLD18-03628
| BLD-Final | 3/25/2019 | 3/25/2019 | 3/25/2019 3:54:51 PM | P | PASS |
|
|
Garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD18-03628
| DOC - Permit Finaled | 3/25/2019 | 3/25/2019 | 3/25/2019 3:54:42 PM | P | PASS |
|
|
All issus resolved.
|
BLD18-03628
| BLD-Blower Door Test Results | 3/25/2019 | 3/25/2019 | 3/25/2019 3:54:29 PM | P | DONE |
|
|
4.2ACH @50pa
|
BLD17-04387
| BLD-Wall Bracing | 3/25/2019 | 3/25/2019 | 3/25/2019 3:23:19 PM | P | PASS |
|
|
Framers are on site with plans Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD18-03023
| BLD-Final | 3/22/2019 | 3/25/2019 | 3/25/2019 2:27:51 PM | P | PASS |
|
|
Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez
|
BLD18-03023
| DOC - Permit Finaled | 3/25/2019 | 3/25/2019 | 3/25/2019 2:27:41 PM | P | PASS |
|
|
|
BLD19-00143
| BLD-Final | 3/25/2019 | 3/25/2019 | 3/25/2019 1:48:27 PM | P | PASS |
|
|
Mike,
Lockbox code is 9701. I scheduled Troy today also for fire. Phone #: ###-#### Inspection requested via web by Todd Kurns. OK for perm occ.
|
BLD19-00470
| BLD-Framing/Rough-in | 3/25/2019 | 3/25/2019 | 3/25/2019 1:30:43 PM | P | FAIL |
|
|
Ed Phone #: ###-####. Repairs done incorrectly. Went over plans with contractor on how to install the blocking and A35's.
|
BLD18-03395
| BLD-Final | 3/25/2019 | 3/25/2019 | 3/25/2019 10:29:19 AM | P | CANC |
|
|
Garage door code is 2468 Phone #: ###-#### >> Inspection requested via web by Joel Hirtle Inspection cancelled from web by: Joel Hirtle
|
BLD19-00729
| BLD-Footing | 3/22/2019 | 3/25/2019 | 3/25/2019 10:26:01 AM | A | PASS |
|
|
Travis Phone #: ###-####. footings for new garage ok.
|
BLD18-03849
| BLD-Final | 3/22/2019 | 3/25/2019 | 3/25/2019 9:16:34 AM | A | PART |
|
|
Please call JP before at ###-####. Phone #: ###-#### Inspection requested via web by Mattie Botero. Ok for temp occ. Per the contractor, no mech. work needed to be completed. need plumbing final
|
BLD18-03684
| BLD-Framing/Rough-in | 3/22/2019 | 3/25/2019 | 3/25/2019 9:01:41 AM | A | PASS |
|
|
Brian Phone #: ###-####. Interior steel stud framed walls for phase 2, restrooms and locker rooms ok.
|
BLD19-00470
| BLD-Framing/Rough-in | 3/22/2019 | 3/25/2019 | 3/25/2019 8:36:51 AM | A | FAIL |
|
|
Ed Phone #: ###-####. Needs to install blocking at every other truss and connect with 2 A35's per the approved drawings and engineering.
|