ELE01-00859
| Electrical Rough-In | 3/22/2001 | 3/26/2001 | 3/26/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/22/2001 at 08:55:56. Contact: ###-####. 1st floor cfu staff room; walls ele r/i. 3/26/2001 10:46:49 AM
|
ELE01-00497
| Electrical Rough-In | 3/23/2001 | 3/26/2001 | 3/26/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 03/23/2001 at 08:39:27. Contact: ###-####. daryl; ###-####. 1st floor resturant managers office ceiling ele r/i. 3/26/2001 9:54:15 AM
|
ELE01-00928
| Final | 3/23/2001 | 3/26/2001 | 3/26/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 03/23/2001 at 14:53:13. Contact: ###-####. PVC in trench ok; shall connect grounding conductor to building steel. 3/26/2001 9:19:52 AM
|
ELE01-00118
| Final | 3/26/2001 | 3/26/2001 | 3/26/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/26/2001 at 08:34:30. Contact: ###-####. completed. ok. 3/26/2001 10:12:23 AM
|
ELE00-04108
| Electrical Rough-In | 3/23/2001 | 3/26/2001 | 3/26/2001 12:00:00 AM | P | PASS |
|
|
###-#### KEY UNDER ROCK AT BACK DOOR 2nd floor ok to cover - left note grd. connection to u-fer needs exposed, 3/26/2001 10:37:26 AM
|