FIR04-00690
| FIR-Aging Inspection | 3/26/2010 | 3/26/2010 | 4/2/2010 9:34:33 AM | | NR |
|
|
Tim Frost sent an email request for status of project.
|
FIR04-00756
| FIR-Aging Inspection | 3/26/2010 | 3/26/2010 | 3/31/2010 10:48:06 AM | | NR |
|
|
Information was forwarded to Scott Arellano for further action.
|
FIR09-00707
| INSP-Sprinkler Rough-in | 3/26/2010 | 3/26/2010 | 3/26/2010 3:28:19 PM | P | PASS |
|
|
see the city approved plans for piping the is ok for cover.
|
FIR10-00014
| INSP-Sprinkler Rough-in | 3/25/2010 | 3/26/2010 | 3/26/2010 1:21:57 PM | A | PASS |
|
|
The sprinkler piping as marked on the plans can be covered. The through bolts for the earth quake bracing have been addressed.
|
BLD09-00945
| FIRE-Final Inspection | 3/26/2010 | 3/26/2010 | 3/26/2010 1:21:07 PM | P | PART |
|
|
Phase 8 life safety passed. The floor plans have been resubmitted and approved for plan modifications as requested. I discussed with Darren that the additional exit signs as marked by the plan reviewer in the phase 9 and 10 area corridors will be required prior to final.
|
BLD10-00354
| FIRE-Conference | 3/25/2010 | 3/26/2010 | 3/26/2010 12:52:44 PM | A | DONE |
|
|
Discussed door hardware issues with Matt.
|
BLD09-01241
| FIRE-Final Inspection | 3/25/2010 | 3/26/2010 | 3/26/2010 11:03:03 AM | A | PASS |
|
|
Life safety passed.
|
FIR09-00534
| INSP-Final Inspection | 3/26/2010 | 3/26/2010 | 3/26/2010 11:02:42 AM | P | PASS |
|
|
Permit finaled
|