Inspections for the day of: Tuesday, March 26, 2013.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-03022 FIRE-Conference3/26/20133/26/20133/28/2013 5:12:53 PMPDONE
On site conversation with contractor regarding fire sprinkler system modifications necessary due to remodel work.
BLD12-02106 FIRE-Final Inspection3/26/20133/26/20133/27/2013 9:09:32 AMPPASS
Scope of work completed. Life safety passed, no signature card available on site.
BLD12-02618 FIRE-Final Inspection3/26/20133/26/20133/27/2013 9:07:28 AMPPASS
Fire life safety finaled. New door hardware can be verified at structural final as discussed.
FIR13-00048 INSP-Final Inspection3/25/20133/26/20133/26/2013 2:53:33 PMAPASS
Scope of fire alarm work passed functional testing. Permit finaled.
BLD13-00490 FIRE-Final Inspection3/25/20133/26/20133/26/2013 2:49:34 PMAFAIL
Correction items include; post exit signage per stamped plans, provide fire extinguisher with current tag as discussed, post "door to remain...." signage at the main entry/exit.
BLD12-01772 FIRE-Conference3/25/20133/26/20133/26/2013 2:46:52 PMADONE
On site conference with contractors regarding plan review red-line comments, fire extinguisher placement, premise identification, entrance gate, etc. A plan modification shoud be done to include the removal of one door between the east side offices and affected exiting.
BLD12-03060 FIRE-Final Inspection3/25/20133/26/20133/26/2013 2:42:46 PMAPASS
Fire life safety final approved.
FIR13-00131 INSP-Final Inspection3/22/20133/26/20133/26/2013 2:41:21 PMAPASS
Field verified corrections are finished. Fire sprinkler permit finaled.
FIR12-00478 FIR-Aging Inspection3/26/20133/26/20133/26/2013 12:12:45 PM CANC