ELE18-01096
| Temporary Service | 3/26/2018 | 3/26/2018 | 3/26/2018 3:07:41 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by jamie berg t/s u/g n ok
|
ELE17-01950
| Electrical Rough-In | 3/23/2018 | 3/26/2018 | 3/26/2018 2:41:18 PM | P | PASS |
|
|
Ceiling Cover. Phone #: ###-#### Inspection requested via web by Buster Bowen Drop ceilings 1st floor minus corridors.
|
ELE18-01059
| Electrical Rough-In | 3/26/2018 | 3/26/2018 | 3/26/2018 2:12:25 PM | P | PASS |
|
|
The pastor of the church, Tim Bridgewater, will be available to let the inspector in. His phone number is ###-####. Phone #: ###-#### Inspection requested via web by Erik Simmons Tamper resistant receps required assembly areas as per 406.12(6) Stage area, changing room and sound booth ok to cover
|
ELE18-01118
| Temporary Service | 3/26/2018 | 3/26/2018 | 3/26/2018 1:47:58 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ben Archibald t/s u/g n ok
|
ELE18-01112
| Temporary Service | 3/26/2018 | 3/26/2018 | 3/26/2018 1:27:58 PM | P | PASS |
|
|
thank you Phone #: ###-#### Inspection requested via web by Bob Glenn t/s u/g n ok
|
ELE17-04253
| Final | 3/26/2018 | 3/26/2018 | 3/26/2018 1:11:20 PM | P | NH |
|
|
Some one should be home Phone #: ###-#### Inspection requested via web by Neal Rumsey No access
|
ELE18-01103
| Electrical Rough-In | 3/25/2018 | 3/26/2018 | 3/26/2018 12:56:49 PM | P | PASS |
|
|
Please call me in the morning and we can set time to meet, in afternoon, at job. Home is occupied so I will need to meet you there. Phone #: ###-#### Inspection requested via web by Kurt Carlson Basement only ok to cover
|
ELE18-00656
| Electrical Rough-In | 3/23/2018 | 3/26/2018 | 3/26/2018 12:04:15 PM | A | PASS |
|
|
Wall cover. Phone #: ###-#### Inspection requested via web by Buster Bowen Walls only ok to cover
|
ELE18-00262
| Electrical Rough-In | 3/23/2018 | 3/26/2018 | 3/26/2018 10:32:04 AM | A | PASS |
|
|
Von is the onsite contact. Phone #: ###-#### Inspection requested via web by Buster Bowen underground in xray room only ok to cover
|
ELE18-01101
| Electrical Rough-In | 3/25/2018 | 3/26/2018 | 3/26/2018 10:18:55 AM | A | PASS |
|
|
There will be someone there finishing low voltage hook ups. Any questions please give David a call. Phone #: ###-#### Inspection requested via web by David Kubik down bath and steamer ok to cover
|
ELE18-01075
| Conference | 3/23/2018 | 3/26/2018 | 3/26/2018 9:52:04 AM | A | PASS |
|
|
Cruz Phone #: ###-#### talked about kitchen lay out, Circuitry, Outside lights and recep required, owner has Homeowner hand out.
|
ELE18-00557
| Electrical Rough-In | 3/26/2018 | 3/26/2018 | 3/26/2018 9:00:18 AM | A | PASS |
|
|
Inspect underground duct bank between Building 36 and Building 51. Contact is Curtis Race ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Duct bank ok to cover
|