ELE19-04516
| Electrical Rough-In | 3/26/2020 | 3/26/2020 | 3/26/2020 12:03:19 PM | P | PASS |
|
|
Unit island under ground raceways Units 140-148 Phone #: ###-#### Inspection requested via web by Stephanie Huston Underground to island receps ok to cover
|
ELE20-01097
| Rough-In Permanent Service | 3/26/2020 | 3/26/2020 | 3/26/2020 11:18:09 AM | A | PASS |
|
|
access project from alley Phone #: ###-#### Inspection requested via web by steve sellers rough in ok p/s o/h n ok
|
ELE20-00485
| Temporary Service | 3/25/2020 | 3/26/2020 | 3/26/2020 10:10:37 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk t/s u/g n ok
|
ELE20-00949
| Rough-In Permanent Service | 3/25/2020 | 3/26/2020 | 3/26/2020 9:14:45 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Troy Ballard NM cable rubbing on gang nail above panel, Loose UFER connection, Mud ring needed for UFER, Service recep needed within 25ft of mini split.
|
ELE19-04505
| Electrical Rough-In | 3/25/2020 | 3/26/2020 | 3/26/2020 8:43:58 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Underground on far E end of parking lot ok to cover
|
ELE20-00083
| Final | 3/24/2020 | 3/26/2020 | 3/25/2020 12:30:27 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kevin Perez Final ok
|