BLD02-00591
| BLD-Footing | 3/26/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | A | PART |
|
|
###-#### JEFF; ext ftgs ok, chk bsmt int ftg at frame insp or? see plan. 3/27/2002 10:53:59 AM
|
MIS02-00039
| BLD-Final | 3/26/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | A | PASS |
|
|
JAMES CELL ###-####...ok for c/o 3/27/2002 12:17:45 PM
|
BLD98-03705
| BLD-Conference | 3/26/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 340 On 3/26/2002 2:54:30 PM
|
BLD01-000-1
| BLD-Final | 3/26/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | A | NR |
|
|
Scheduled by Inspector: 340 On 3/26/2002 4:40:08 PM 7130977 reschedule 3/27/2002 8:59:45 AM
|
BLD01-03253
| BLD-Framing/Rough-in | 3/27/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | P | PART |
|
|
###-#### CHRIS CALL 1ST PLEASE; grid ok pending hvac ok; keep c/n re chk 4hr wall at canopy o.h. 3/27/2002 4:25:47 PM
|
BLD01-000-1
| BLD-Final | 3/27/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 340 On 3/27/2002 8:59:13 AM c/n, handrail extensions, misc finish, obtain permanent finals, ok for t/o. 3/27/2002 3:22:07 PM
|
BLD01-00000
| BLD-Final | 3/27/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | P | PART |
|
|
Added by Inspector: 340 On 3/27/2002 3:20:42 PM c/n, handrail extensions, caulk-seal penetrations, complete misc finish items & obtain other permanent finals...ok for t/o
|
MIS02-00069
| BLD-Conference | 3/27/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | P | FAIL |
|
|
Carl D. and I posted this property requireing a CO.
|
BLD01-02821
| BLD-Final | 3/26/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | P | FAIL |
|
|
###-#### TONY install ADA & exit signage, obtain other finals . 3/27/2002 1:34:36 PM 3/27/2002 1:34:56 PM
|
BLD01-03276
| BLD-Final | 3/26/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | P | PASS |
|
|
###-#### l/c issued, mech n.a....fire ok. 3/27/2002 4:56:12 PM
|
BLD02-00164
| BLD-Framing/Rough-in | 3/26/2002 | 3/27/2002 | 3/27/2002 12:00:00 AM | P | FAIL |
|
|
###-####...see c/n 3/27/2002 6:30:38 PM
|