FIR06-00474
| FIR-Aging Inspection | 3/27/2008 | 3/27/2008 | 3/28/2008 3:46:29 PM | P | DONE |
|
|
Peak alarm to schedule testing for final acceptance of permit work.
|
FIR08-00165
| INSP-Sprinkler Rough-in | 3/27/2008 | 3/27/2008 | 3/28/2008 3:45:24 PM | P | PART |
|
|
System modifications are acceptable at areas as circled and initialed on plan set, three training rooms to the west side are not yet complete.
|
BLD06-00693
| FIRE-Final Inspection | 3/27/2008 | 3/27/2008 | 3/28/2008 3:42:52 PM | P | PASS |
|
|
Items on correction notice are complete, structrual inspector to verifiy adjusted door closures at apartment units are acceptable, fire life safety finaled.
|
BLD05-00926
| FIRE-Final Inspection | 3/27/2008 | 3/27/2008 | 3/28/2008 3:40:56 PM | P | PASS |
|
|
Fire life safety finaled.
|
FIR08-00113
| INSP-Final Inspection | 3/27/2008 | 3/27/2008 | 3/27/2008 5:23:51 PM | P | FAIL |
|
|
Need to relocate the pendent head at the north utility room due to cabinet obstruction.
|
FIR08-00089
| INSP-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 5:21:50 PM | P | FAIL |
|
|
Need to relocate or remove the smoke detector at the new nac panel, noted some overspaced notification devices, tenant floorplan has been modified to include an adjacent space-building permit is under review for approval. No alarm testing completed today.
|
FIR08-00088
| INSP-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 5:16:13 PM | P | FAIL |
|
|
Drawings do not match floorplan, one workroom not shown on plans will need notification, noted overspaced strobes at three locations, one av has been deleted due to room changes, no devices tested at this time.
|
FIR06-00540
| INSP-Final Inspection | 3/25/2008 | 3/27/2008 | 3/27/2008 4:22:54 PM | P | NR |
|
|
|
FIR06-00595
| INSP-Final Inspection | 3/27/2008 | 3/27/2008 | 3/27/2008 4:22:01 PM | P | NR |
|
|
Inspection to be rescheduled.
|
BLD07-03251
| FIRE-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 4:21:15 PM | P | PART |
|
|
Fire life safety field inspection completed satisfactory, final pending project related fire alarm final for verification of corrected defficiencies and FA interconnection to mag locks for access controled egress at three locations, also missing permanent max. occupant load signs at one assembly room.
|
FIR08-00051
| INSP-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 4:16:55 PM | P | PASS |
|
|
Fire sprinkler permit final inspection passed.
|
FIR08-00095
| INSP-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 2:21:15 PM | P | PASS |
|
|
Tenant remodel fire alarm testing passed inspection, permit finaled.
|
FIR08-00039
| INSP-Sprinkler Rough-in | 3/26/2008 | 3/27/2008 | 3/27/2008 1:54:50 PM | A | FAIL |
|
|
One upright head at the womens restroom is blocked by adjacent ductwork, one ssu at the mens restroom is obstructed by the top joist cord which extends below and directly next to the deflector, missing EQ brace at the last piece of main. Areas approved for cover include the hall 116, sacristy 115, and the narthex entry 101-see stamped plans for initialed locations. Also verified resubmittals match installation at areas where field modifications were done.
|
BLD08-00056
| FIRE-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 12:52:25 PM | A | PASS |
|
|
Fire life safety inspection passed. Fire alarm work tested per separate permit and completed final by K. Roule.
|
FIR07-01012
| FIR-Aging Inspection | 3/27/2008 | 3/27/2008 | 3/27/2008 12:47:54 PM | | DONE |
|
|
Work in progress, pending site inspection request.
|
FIR07-00835
| INSP-Supply line flush | 3/26/2008 | 3/27/2008 | 3/27/2008 12:47:00 PM | P | PART |
|
|
UG fire supply line flush completed satisfactory post hydrostatic test.
|
FIR08-00207
| INSP-Sprinkler Rough-in | 3/26/2008 | 3/27/2008 | 3/27/2008 12:45:33 PM | A | PART |
|
|
OH fire sprinkler system modifications are approved for cover at the drop ceilings, minor floorplan changes and sprinkler head location adjustments accepted, final pending ceiling tile and escutcheons.
|
FIR07-00835
| INSP-Sprinkler Rough-in/Hydro | 3/26/2008 | 3/27/2008 | 3/27/2008 12:43:24 PM | A | PART |
|
|
UG fire supply line hydrostatic test passed inspection.
|
FIR08-00117
| INSP-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 12:42:30 PM | A | PART |
|
|
Scope of work is not complete due to pending demolition of the photo room, conference room pendent heads are satisfactory. Also noted non-functional outside waterflow bell to be repaired and verified at next site visit for permit final.
|
FIR07-00958
| INSP-Sprinkler Rough-in | 3/26/2008 | 3/27/2008 | 3/27/2008 12:34:50 PM | A | FAIL |
|
|
Red-lined areas on stamped plan set in need of revision prior to approval for cover including blocked or overspaced upright heads at various locations and missing coverage at a storage room. Not all areas ready for inspection at this time, see plans for annotations.
|
FIR08-00205
| INSP-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 8:12:49 AM | P | CANC |
|
|
mike Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
|
FIR08-00207
| INSP-Supply line flush | 3/26/2008 | 3/27/2008 | 3/27/2008 12:00:00 AM | A | CANC |
|
|
ben Phone #: ###-####
|