Inspections for the day of: Thursday, March 27, 2008.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00184 INSP-Sprinkler Rough-in/Hydro3/27/20083/27/20083/28/2008 8:34:51 AMPPASS
Sprinkler piping is ok to cover
FIR07-00968 FIR-Aging Inspection3/27/20083/27/20083/27/2008 4:44:59 PM NR
work is in progress
FIR07-00579 INSP-Sprinkler Rough-in/Hydro3/26/20083/27/20083/27/2008 4:43:26 PMPPASS
OH Hydro Inspection for the gym area passed.
FIR08-00171 INSP-Final Inspection3/27/20083/27/20083/27/2008 4:04:00 PMPPASS
Permit finaled
FIR07-00949 INSP-Sprinkler Rough-in3/26/20083/27/20083/27/2008 4:03:25 PMAFAIL
The tenting is still inadequate. There are locations where the piping is not covered.
FIR07-00510 INSP-Alarm Testing3/26/20083/27/20083/27/2008 4:02:05 PMADONE
See the city approved plans for items tested today and for the defieciencies noted.
BLD07-03252 FIRE-Final Inspection3/26/20083/27/20083/27/2008 1:06:59 PMAFAIL
Provide additional emergency lights as marked on the plans and repair the emergency lights as marked on the plans. Provide a clear fire alarm panel. Install the missing ceiling tile and missing sprinkler canopies.
FIR07-00929 INSP-Sprinkler Rough-in3/26/20083/27/20083/27/2008 8:57:26 AMAPASS
Underground flush passed