Inspections for the day of: Thursday, March 27, 2014.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00519 INSP-Final Inspection3/26/20143/27/20143/27/2014 3:29:07 PMPFAIL
Everything is complete except the unknown signals from zone one need addressed as per the fire dept.
FIR13-00177 INSP-Sprinkler Rough-in3/27/20143/27/20143/27/2014 3:15:48 PMPPASS
See the city approved plans for restroom location where piping can be covered.
FIR14-00054 INSP-Sprinkler Rough-in/Hydro3/26/20143/27/20143/27/2014 3:15:07 PMAFAIL
Need to provide a Knox Box as per the approved plans and discussion. Need to make the monitoring account "live".
BLD12-01914 FIRE-Conference3/27/20143/27/20143/27/2014 2:30:43 PMPDONE
brad turk and I discussed existing
FIR13-00618 INSP-Sprinkler Rough-in3/25/20143/27/20143/27/2014 2:27:47 PMPPASS
Overhead rough-in passed. Will need a cover inspection once the pendant heads in the office area are installed. It appears that branchline restraints will be required and the combustible concealed space at the front entrance will need addressed. Mike stated that they are resubmitting showing the column protection and the relocation of the east main (office area).
BLD13-02969 FIRE-Final Inspection3/27/20143/27/20143/27/2014 2:14:17 PMPPASS
life safety passed
FIR14-00014 INSP-Final Inspection3/26/20143/27/20143/27/2014 12:15:31 PMAPASS
permit finaled
FIR14-00104 INSP-Final Inspection3/26/20143/27/20143/27/2014 12:08:17 PMAPASS
Permit finaled. FACP only capable of alarm and supervisory per tech.
FIR14-00105 INSP-Final Inspection3/26/20143/27/20143/27/2014 12:07:11 PMAPASS
Permit finaled. FACP only capable of alarm and trouble per tech.
BLD12-02487 FIRE-Final Inspection3/26/20143/27/20143/27/2014 9:30:23 AMAPASS
Life safety passed