Inspections for the day of: Friday, March 27, 2015.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00750 INSP-Sprinkler Rough-in3/27/20153/27/20153/31/2015 11:53:48 AMPPART
Inspection to verify completion of previously noted correction items at the dry system. Finished 3/27.
FIR15-00096 INSP-Sprinkler Rough-in3/26/20153/27/20153/31/2015 11:43:59 AMPPART
Ref. to inspection notes dated 3/30
FIR14-00866 INSP-Sprinkler Rough-in3/26/20153/27/20153/31/2015 11:42:15 AMPPART
Completed rough-in inspection for the remainder of the 4th floor living units only as noted on stamped plans. Items noted include; overspaced coverage at unit 405, missing coverage at units 430 and 432. Need to install flushing caps per plan notes.
BLD14-03666 FIRE-Final Inspection3/25/20153/27/20153/27/2015 2:07:37 PMAPART
Final pending door hardware and posting of one fire extinguisher per plan. Remainder okayed.
BLD14-03595 FIRE-Final Inspection3/27/20153/27/20153/27/2015 1:24:46 PMPPASS
Fire life safety inspection passed.
FIR14-00889 INSP-Final Inspection3/26/20153/27/20153/27/2015 1:04:48 PMAPASS
Completed dry system trip test, riser supervision, final walkthrough and verification of noted correction items.
FIR14-00243 INSP-Final Inspection3/26/20153/27/20153/27/2015 1:00:27 PMAPASS
Remainder of fire alarm work passed final inspection and testing.
FIR14-00316 INSP-Final Inspection3/26/20153/27/20153/27/2015 10:44:01 AMANH
No access
FIR14-00437 INSP-Final Inspection3/26/20153/27/20153/27/2015 10:42:06 AMANH
No access to complete inspection
BLD14-03715 FIRE-Final Inspection3/25/20153/27/20153/27/2015 10:40:20 AMAPASS
Fire life safety inspection completed. However cannot be finaled until project related fire alarm work is inspected and approved. Also noted missing smoke seal at the main entry corridor door frame.
FIR15-00109 INSP-Final Inspection3/25/20153/27/20153/27/2015 10:35:54 AMAPASS
Fire sprinkler permit work passed final walkthrough.
FIR15-00186 INSP-Final Inspection3/26/20153/27/20153/27/2015 7:15:12 AMAPASS
Fire sprinkler permit work finaled.
FIR15-00186 INSP-Sprinkler Rough-in3/26/20153/27/20153/26/2015 5:54:45 PMAPART
Fire sprinkler modifications okay for cover.