BLD17-03023
| FIRE-Conference | 3/27/2018 | 3/27/2018 | 3/27/2018 3:29:19 PM | P | DONE |
|
|
The Main Stage and the Audio/Visual Stage have both been filled with insulation and now will not require fire sprinkler protection.
Matt Phone #: ###-####
|
FIR17-00309
| INSP-Sprinkler Rough-in | 3/26/2018 | 3/27/2018 | 3/27/2018 3:28:16 PM | A | PART |
|
|
Installation for the most part is ok. One four way brace at the top of Stair #2 is missing as well as flexible cplgs through a CMU wall. The position of the hose valves in Stair #1 need to be relocated (swung) as per conversation away from the roof drain line as well as possible drainage concerns. It appears the FDC and drain out of the west side of the building interferes with the stairwell door and will need to be relocated.
Todd Ketterling is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR16-00708
| INSP-Final Inspection | 3/21/2018 | 3/27/2018 | 3/27/2018 2:24:42 PM | A | DONE |
|
|
Today was a partial inspection. I looked at the control equipment and one first floor wing of the system. I noted that a different FACP panel has been installed, a different communication method has been installed, of the nine NAC panels installled two are different from the rest, all nine are triggered from a single module which is not shown on the plans, the trouble signals are being monitored by two monitor modules that are not shown on the plans, breaker lock is missing, one wall mounted a/v is overspaced as marked on plans, notification needs to be added in the Office with three people in it as marked on the plans. Again this was a partial inspection.
Ray McQueen, inspection technician; building has open availability Phone #: ###-#### Inspection requested via web by Rose Peterson
|
FIR18-00222
| INSP-Final Inspection | 3/20/2018 | 3/27/2018 | 3/27/2018 2:19:00 PM | A | FAIL |
|
|
Need a 12ah battery as per plans
|
BLD16-04079
| FIRE-Final Inspection | 3/26/2018 | 3/27/2018 | 3/27/2018 10:34:34 AM | A | PASS |
|
|
life safety passed
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
FIR17-00303
| INSP-Final Inspection | 3/26/2018 | 3/27/2018 | 3/27/2018 10:33:21 AM | A | PASS |
|
|
permit finaled
Todd Ketterling is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR17-00584
| INSP-Final Inspection | 3/26/2018 | 3/27/2018 | 3/27/2018 10:31:56 AM | A | PASS |
|
|
Permit finaled
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
FIR18-00218
| INSP-Final Inspection | 3/26/2018 | 3/27/2018 | 3/27/2018 8:08:05 AM | A | FAIL |
|
|
Called twice, left one message, left project after meeting time was expended
Zach Phone #: ###-#### Inspection requested via web by Don Kartchner
|
FIR18-00243
| INSP-Sprinkler Rough-in | 3/26/2018 | 3/27/2018 | 3/27/2018 7:30:31 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered.
Rick Phone #: ###-####
|