FIR05-00239
| INSP-Supply line flush | 3/27/2006 | 3/28/2006 | 3/28/2006 4:45:49 PM | P | PART |
|
|
UG supply line flush performed satisfactory.
|
FIR06-00073
| INSP-Sprinkler Rough-in/Hydro | 3/28/2006 | 3/28/2006 | 3/28/2006 4:44:59 PM | A | PART |
|
|
UG supply line hydrostatic test inspection passed.
|
FIR05-00594
| INSP-Sprinkler Rough-in | 3/24/2006 | 3/28/2006 | 3/28/2006 12:21:07 PM | A | PART |
|
|
Pump start-up testing performed with manufacturer rep. including churn, rated and 150 percent capacity, manual and automatic starts and stops, jockey pump, set pressures, event log, min. run time, sensing lines, piping arrangements. Performance testing only, no alarm, trouble or supervised conditions tested at this time.
|
FIR05-00239
| INSP-Sprinkler Rough-in | 3/27/2006 | 3/28/2006 | 3/28/2006 12:12:07 PM | A | PART |
|
|
UG hydrostatic test passed inspection.
|
FIR06-00053
| INSP-Sprinkler Rough-in | 3/27/2006 | 3/28/2006 | 3/28/2006 9:02:07 AM | A | FAIL |
|
|
The yard post indicator is below min. height requirements above finish grade, need to cap ductile riser piece, provide seismic clearance at floor slab. Thrust blocks are acceptable, the majority of UG pipe run was covered prior to inspection.
|