FIR12-00055
| INSP-Final Inspection | 3/28/2012 | 3/28/2012 | 3/30/2012 10:58:58 AM | P | PART |
|
|
Functional testing including offsite monitoring completed satisfactory. Note, a plan modification will be necessary due to installation of a remote annunciator. Location of the RA to be per section 510.2 of title 7 municipal code amendments.
|
BLD11-01695
| FIRE-Conference | 3/27/2012 | 3/28/2012 | 3/30/2012 10:53:27 AM | P | DONE |
|
|
On site visit regarding knox box, fire dept. access, fire code review notes, project related fire alarm work, etc.
|
FIR12-00141
| INSP-Final Inspection | 3/28/2012 | 3/28/2012 | 3/29/2012 10:24:28 AM | P | PASS |
|
|
Fire sprinkler permit final approved.
|
BLD11-02686
| FIRE-Final Inspection | 3/28/2012 | 3/28/2012 | 3/29/2012 10:23:16 AM | P | PASS |
|
|
Fire life safety finaled.
|
FIR12-00141
| INSP-Final Inspection | 3/28/2012 | 3/28/2012 | 3/28/2012 12:02:32 PM | A | PASS |
|
|
Final walkthrough completed. Inspection passed.
|
BLD11-02686
| FIRE-Final Inspection | 3/27/2012 | 3/28/2012 | 3/28/2012 12:01:13 PM | A | FAIL |
|
|
Correction items include one non-functional exit sign at the north exit, remove hasp and padlock at the second exit door.
|
BLD12-00197
| FIRE-Conference | 3/28/2012 | 3/28/2012 | 3/28/2012 11:56:46 AM | A | DONE |
|
|
Regarding project related FIR permits and schedule for fire life safety inspection items.
|
FIR11-00431
| INSP-Sprinkler Rough-in/Hydro | 3/27/2012 | 3/28/2012 | 3/28/2012 11:54:53 AM | A | NR |
|
|
Need hydrostatic test. Plan modification required for field changes to the approved design including added heads in the calc. area- ref. activity notes dated 2/22/12.
|
FIR11-00658
| INSP-Sprinkler Rough-in/Hydro | 3/27/2012 | 3/28/2012 | 3/28/2012 11:51:12 AM | A | FAIL |
|
|
Noted pressure loss at the guage and a leaking coupling on the system side. Missing seismic bracing at the mains.
|