Inspections for the day of: Tuesday, March 28, 2017.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00510 INSP-Supply line flush3/27/20173/28/20173/28/2017 2:33:16 PMPDONE
Underground main line flush completed
FIR16-00509 INSP-Supply line flush3/27/20173/28/20173/28/2017 2:32:58 PMPDONE
Underground main supply flush completed
FIR16-00400 INSP-Final Inspection3/28/20173/28/20173/28/2017 2:28:40 PMPPASS
Final fire alarm inspection passed/complete
FIR16-00028 INSP-Final Inspection3/28/20173/28/20173/28/2017 2:28:14 PMPPASS
Final fire sprinkler inspection passed/complete
FIR16-00512 INSP-Sprinkler Rough-in/Hydro3/27/20173/28/20173/28/2017 2:26:40 PMPCANC
First Floor Hydro cancelled due to test pump issues, hydro will be rescheduled
FIR16-00437 INSP-Final Inspection3/28/20173/28/20173/28/2017 1:01:16 PMPPASS
Final fire alarm inspection passed/complete
FIR16-00707 INSP-Final Inspection3/27/20173/28/20173/28/2017 12:58:58 PMPCANC
Inspection rescheduled to coincide with life fire safety inspection
BLD16-00172 FIRE-Final Inspection3/27/20173/28/20173/28/2017 12:50:10 PMAPART
Life fire safety Inspection for requested TCO complete (Levels 2 and 4). Building has active fire sprinklers throughout to include monitoring, final inspection for fire sprinklers in requested TCO area's with exception to some heads that will be installed at a later date, final fire alarm inspection has been completed for TCO requested area's (fire alarms are active on floors above and below TCO requested floors 2 and 4), fire extinguishers are in place with current inspection tags, knox box is on order and will be installed when received. Area's that have not had a final inspection performed are the basement level, level 1, mezzanine level and level 3. Life fire safety inspection passed for levels 2 and 4.