Inspections for the day of: Tuesday, March 29, 2011.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC10-00383 DOC - Permit Finaled3/29/20113/29/20113/29/2011 4:15:56 PMPPASS
Project is complete.
ESC05-01787 Aging Inspection3/29/20113/29/20113/29/2011 1:47:22 PM DONE
Permit finaled.
ESC05-01787 DOC - Permit Finaled3/29/20113/29/20113/29/2011 1:47:12 PMPPASS
ESC05-01599 Aging Inspection3/29/20113/29/20113/29/2011 1:45:09 PM DONE
ESC05-01599 DOC - Permit Finaled3/29/20113/29/20113/29/2011 1:45:02 PMPPASS
ESC05-01203 Aging Inspection3/29/20113/29/20113/29/2011 1:07:45 PM DONE
Permit finalled.q
ESC05-01203 DOC - Permit Finaled3/29/20113/29/20113/29/2011 1:07:36 PMPPASS
ESC05-01587 Aging Inspection3/29/20113/29/20113/29/2011 1:07:26 PM DONE
Permit expired.
ESC05-01587 DOC - Permit Expired3/29/20113/29/20113/29/2011 1:07:15 PMPPASS
ESC10-00605 General Inspection3/29/20113/29/20113/29/2011 10:13:58 AM PASS
ESC10-00603 General Inspection3/29/20113/29/20113/29/2011 10:12:27 AM DONE
No activity
ESC10-00186 BMP Violation3/24/20113/29/20113/29/2011 9:55:35 AMADONE
Confrence with RP:
1. Maintain the access control along Shoup.
2. Add additional rock for access to the washout pit and maintain the washout pit due to being over 50% capacity.
3. Clean upp all hard surfaces in the active vertical constrution area on a daily basis. Will re-inspect on 3/ 31/2011