Inspections for the day of: Tuesday, March 29, 2016.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEvan Jenkins
TitleEROSION CONTROL MANAGER
Phone #794-3958
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00094 Site Preparation3/29/20163/29/20163/29/2016 1:51:38 PMPCANC
Shane ###-####

Per RP Request. RP will reschedual when he is ready to break ground later this week.
ESC16-00292 Site Preparation3/29/20163/29/20163/29/2016 1:23:38 PMPPASS
Bryan Phone #: ###-####

Permit posted on porta pot infront of flat lot.
Approved for construction
ESC16-00315 Complaint Inspection3/29/20163/29/20163/29/2016 12:57:51 PMAPART
Complaint from Demo Dust leaving site via Code Enforcement

When inspected, most the house was Demoed, and dust was very minimal. Contractor had a garden hose onsite watering down the debris to reduce dust. Demo Near completion
ESC15-00818 General Inspection3/29/20163/29/20163/29/2016 11:44:26 AM PEND
re-veg
ESC16-00211 Site Preparation3/28/20163/29/20163/29/2016 9:53:19 AMAPASS
Brandon Phone #: ###-####

Permit Posted in front of lot
Concrete washout located in other phase of sub.
Approved for Construction
ESC16-00212 Site Preparation3/28/20163/29/20163/29/2016 9:52:59 AMAPASS
Brandon Phone #: ###-####

Permit Posted in front of lot
Concrete washout located in other phase of sub.
Approved for Construction
ESC15-00609 Aging Inspection3/29/20163/29/20163/29/2016 9:25:54 AM PASS
ESC15-00894 General Inspection3/29/20163/29/20163/29/2016 8:37:32 AM PASS
ESC15-00893 General Inspection3/29/20163/29/20163/29/2016 8:35:43 AM PASS