BLD17-00770
| FIRE-Final Inspection | 3/29/2017 | 3/29/2017 | 3/29/2017 2:02:09 PM | P | PASS |
|
|
No modifications to fire sprinklers, no modifications to fire alarm system, fire extinguishers are in place with current inspection tags, commercial hood fire suppression system has a current inspection tag. Final life fire safety inspection passed/complete.
|
BLD16-02292
| FIRE-Final Inspection | 3/29/2017 | 3/29/2017 | 3/29/2017 1:34:56 PM | P | PASS |
|
|
No fire sprinklers, no fire alarm modifications, fire extinguisher is mounted with a current inspection tag (Inspection tag expires next month, extinguisher will need to be inspected by then) building does have a knox box mounted be main entrance. Final life fire safety inspection passed/complete.
|
BLD16-01265
| FIRE-Final Inspection | 3/22/2017 | 3/29/2017 | 3/29/2017 11:07:55 AM | A | PART |
|
|
Partial final for life fire safety inspection passed/complete. Exit lights currently in place are temporary and not rated for outdoor use, exit lights rated for outdoor use are on order and will be installed when received. Life fire safety can be signed off after outdoor rated exit lights are installed and inspected.
|
BLD14-01818
| FIRE-Final Inspection | 3/22/2017 | 3/29/2017 | 3/29/2017 11:04:34 AM | A | PASS |
|
|
Exit discharge to pool area is complete, final life fire safety inspection passed/complete.
|
BLD14-01825
| FIRE-Final Inspection | 3/22/2017 | 3/29/2017 | 3/29/2017 11:03:54 AM | A | PASS |
|
|
Exit discharge to pool area is complete, final life fire safety inspection passed/complete.
|
FIR16-00088
| INSP-Sprinkler Rough-in | 3/28/2017 | 3/29/2017 | 3/29/2017 10:42:39 AM | A | PART |
|
|
Rough to cover inspection for fire sprinkler piping/pendant heads in lobby area complete, approved for cover.
|
BLD15-04468
| FIRE-Final Inspection | 3/27/2017 | 3/29/2017 | 3/29/2017 10:15:00 AM | P | CANC |
|
|
Scheduled for 8AM on 30MAR2017
|
FIR17-00114
| INSP-Final Inspection | 3/29/2017 | 3/29/2017 | 3/29/2017 10:12:47 AM | P | CANC |
|
|
Scheduled for 30MAR2017
|
FIR16-00707
| INSP-Sprinkler Rough-in/Hydro | 3/28/2017 | 3/29/2017 | 3/29/2017 10:11:08 AM | A | PART |
|
|
Fire sprinkler work for requested TCO area's complete (Link between GBAD, Century Link Arena, Boise Center on the Grove as well as escalators from link and lobby are for escalator discharge)
|
FIR16-00701
| INSP-Sprinkler Rough-in | 3/28/2017 | 3/29/2017 | 3/29/2017 10:02:00 AM | P | PART |
|
|
Partial rough to cover inspection complete for south east underground, approved for cover.
|
FIR16-00088
| INSP-Sprinkler Rough-in/Hydro | 3/28/2017 | 3/29/2017 | 3/28/2017 1:37:43 PM | P | CANC |
|
|
Hydro on town homes rough to cover on lobby. Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|