Inspections for the day of: Wednesday, March 29, 2017.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-00770 FIRE-Final Inspection3/29/20173/29/20173/29/2017 2:02:09 PMPPASS
No modifications to fire sprinklers, no modifications to fire alarm system, fire extinguishers are in place with current inspection tags, commercial hood fire suppression system has a current inspection tag. Final life fire safety inspection passed/complete.
BLD16-02292 FIRE-Final Inspection3/29/20173/29/20173/29/2017 1:34:56 PMPPASS
No fire sprinklers, no fire alarm modifications, fire extinguisher is mounted with a current inspection tag (Inspection tag expires next month, extinguisher will need to be inspected by then) building does have a knox box mounted be main entrance. Final life fire safety inspection passed/complete.
BLD16-01265 FIRE-Final Inspection3/22/20173/29/20173/29/2017 11:07:55 AMAPART
Partial final for life fire safety inspection passed/complete. Exit lights currently in place are temporary and not rated for outdoor use, exit lights rated for outdoor use are on order and will be installed when received. Life fire safety can be signed off after outdoor rated exit lights are installed and inspected.
BLD14-01818 FIRE-Final Inspection3/22/20173/29/20173/29/2017 11:04:34 AMAPASS
Exit discharge to pool area is complete, final life fire safety inspection passed/complete.
BLD14-01825 FIRE-Final Inspection3/22/20173/29/20173/29/2017 11:03:54 AMAPASS
Exit discharge to pool area is complete, final life fire safety inspection passed/complete.
FIR16-00088 INSP-Sprinkler Rough-in3/28/20173/29/20173/29/2017 10:42:39 AMAPART
Rough to cover inspection for fire sprinkler piping/pendant heads in lobby area complete, approved for cover.
BLD15-04468 FIRE-Final Inspection3/27/20173/29/20173/29/2017 10:15:00 AMPCANC
Scheduled for 8AM on 30MAR2017
FIR17-00114 INSP-Final Inspection3/29/20173/29/20173/29/2017 10:12:47 AMPCANC
Scheduled for 30MAR2017
FIR16-00707 INSP-Sprinkler Rough-in/Hydro3/28/20173/29/20173/29/2017 10:11:08 AMAPART
Fire sprinkler work for requested TCO area's complete (Link between GBAD, Century Link Arena, Boise Center on the Grove as well as escalators from link and lobby are for escalator discharge)
FIR16-00701 INSP-Sprinkler Rough-in3/28/20173/29/20173/29/2017 10:02:00 AMPPART
Partial rough to cover inspection complete for south east underground, approved for cover.
FIR16-00088 INSP-Sprinkler Rough-in/Hydro3/28/20173/29/20173/28/2017 1:37:43 PMPCANC
Hydro on town homes rough to cover on lobby. Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball