ELE19-01083
| Final | 3/29/2019 | 3/29/2019 | 3/29/2019 2:38:01 PM | P | CANC |
|
|
final for panel and new circuit....rescheduled to 4/01/19
|
ELE17-00009
| ELE-Aging Inspection | 3/29/2019 | 3/29/2019 | 3/29/2019 2:29:36 PM | | PASS |
|
|
extended permit
|
ELE17-00009
| ELE-Request for Extension | 3/29/2019 | 3/29/2019 | 3/29/2019 2:29:10 PM | P | PASS |
|
|
spoke with permit holder...extension requested...still under construction
|
ELE19-01090
| Final | 3/28/2019 | 3/29/2019 | 3/29/2019 2:16:58 PM | P | PASS |
|
|
We are doing a shut down ; meter repair by replacing either the jaw or the whole socket which ever one is best cooperative! I will give you a call as soon as its complete! Thx. Steve, BPL Phone #: ###-#### Inspection requested via web by Steven Meredith... lugs tightened...meter reinstalled...ok
|
ELE19-00959
| Electrical Rough-In | 3/29/2019 | 3/29/2019 | 3/29/2019 1:51:24 PM | P | PASS |
|
|
Steve Phone #: ###-####... ok to cover and proceed a 2nd rough inspection will be needed to verify make up of wires in boxes live at residence while performing work
|
ELE19-01086
| Conference | 3/29/2019 | 3/29/2019 | 3/29/2019 1:00:11 PM | P | PASS |
|
|
Tim Phone #: ###-####... discussed wiring of new bedroom, bathroom and living rm...pamphlet given...homeowner with help of brother in law competent
|
ELE19-01038
| Final | 3/29/2019 | 3/29/2019 | 3/29/2019 11:38:20 AM | P | CANC |
|
|
I Was Out Sick Sorry I Will make Correction This Morning Thanks Dave Phone #: ###-#### Inspection requested via web by jason shifflett... wrong inspection...needed temp service
|
ELE19-01038
| Temporary Service | 3/29/2019 | 3/29/2019 | 3/29/2019 11:37:52 AM | P | PASS |
|
|
I Was Out Sick Sorry I Will make Correction This Morning Thanks Dave Phone #: ###-#### Inspection requested via web by jason shifflett... t/s u/g new ok
|
ELE19-00772
| Final | 3/29/2019 | 3/29/2019 | 3/29/2019 11:13:48 AM | P | PASS |
|
|
ok to final
|
ELE19-00608
| Final | 3/29/2019 | 3/29/2019 | 3/29/2019 11:04:35 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Greg Traudt... ok to final
|
ELE19-01083
| Conference | 3/28/2019 | 3/29/2019 | 3/29/2019 10:30:55 AM | A | PASS |
|
|
Tim Phone #: ###-####... discussed panel change and new circuit location replacing same amperage
|
ELE19-00608
| Final | 3/29/2019 | 3/29/2019 | 3/29/2019 10:24:05 AM | P | CANC |
|
|
mess up
|
ELE18-02665
| Electrical Rough-In | 3/28/2019 | 3/29/2019 | 3/29/2019 9:50:46 AM | A | PASS |
|
|
Contact: Rich Bail Phone #: ###-#### Inspection requested via web by Deb Gooden... ceiling ok NE locker room area
|
ELE19-00772
| Electrical Rough-In | 3/28/2019 | 3/29/2019 | 3/29/2019 9:02:02 AM | A | PASS |
|
|
Requesting 9:00 am inspection time. Install of 1 wall sign Phone #: ###-#### Inspection requested via web by Ken Olsen... UL listed and disconnect
|
ELE19-00966
| Final | 3/28/2019 | 3/29/2019 | 3/29/2019 8:44:14 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Shawna Gates... ok to final
|
ELE18-04245
| Electrical Rough-In | 3/28/2019 | 3/29/2019 | 3/29/2019 8:19:49 AM | A | PASS |
|
|
Inspect bathroom ceilings for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud... ok to cover
|