Inspections for the day of: Friday, March 3, 2000.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorGary Ziegler
TitlePLM-INSPECTOR
Phone #794-9379
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM00-00562 Plumbing Rough-in3/2/20003/3/20003/3/2000 12:00:00 AMAPASS
Rob ###-####
PLM00-00564 Plumbing Rough-in3/2/20003/3/20003/3/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 03/02/2000 at 14:20:02. Contact: ###-####.
PLM00-00549 Water and/or Sewer3/2/20003/3/20003/3/2000 12:00:00 AMAPASS
###-####
PLM00-00505 Plumbing Rough-in3/2/20003/3/20003/3/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 03/02/2000 at 16:05:01. Contact: ###-####.
PLM00-00023 Groundwork3/2/20003/3/20003/3/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 03/02/2000 at 16:05:48. Contact: ###-####. Sewer to future Albertsons Express 3/6/00 11:14:14 AM
PLM99-04123 Plumbing Rough-in3/2/20003/3/20003/3/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 03/02/2000 at 16:33:02. Contact: ###-####.---LATE AM????
PLM00-00023 Groundwork3/3/20003/3/20003/3/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 03/03/2000 at 10:58:28. Contact: ###-####. RE route main sewer. 3/6/00 11:14:30 AM
PLM00-00505 Plumbing Rough-in3/3/20003/3/20003/3/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 03/03/2000 at 11:19:46. Contact: ###-####.