FIR14-00778
| INSP-Sprinkler Rough-in | 3/2/2015 | 3/3/2015 | 3/6/2015 2:45:39 PM | P | PART |
|
|
|
FIR14-00708
| INSP-Sprinkler Rough-in | 3/2/2015 | 3/3/2015 | 3/6/2015 2:44:57 PM | P | PART |
|
|
|
FIR14-00344
| INSP-Sprinkler Rough-in | 3/2/2015 | 3/3/2015 | 3/3/2015 4:38:39 PM | P | PART |
|
|
Completed overhead inspection for cover at the 2nd floor building areas A, B, and C for sheetrock lids at the corridor, service use rooms, and common areas as marked and dated on approved plans. Items noted include; one head to be relocated, missing hanger at the 2" main in housekeeping, relocate capped drop, SW heads at area A in three locations are not yet installed. Discussed max head spacing at the corridors, locations per plan where standard pendent heads are to be provided, proximity of light fixture junction boxes to sprinklers.
|
BLD14-03308
| FIRE-Final Inspection | 3/2/2015 | 3/3/2015 | 3/3/2015 4:31:20 PM | P | PASS |
|
|
Fire life safety inspection completed acceptable. Need to post tenant space suite address numbers prior to structural final as discussed.
|
FIR15-00101
| INSP-Final Inspection | 3/2/2015 | 3/3/2015 | 3/3/2015 4:29:38 PM | P | PASS |
|
|
Fire alarm testing completed satisfactory. As-builts recieved.
|
FIR15-00016
| INSP-Final Inspection | 3/2/2015 | 3/3/2015 | 3/3/2015 4:28:37 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|