ELE12-01594
| ELE-Aging Inspection | 3/3/2016 | 3/3/2016 | 3/4/2016 10:37:43 AM | | DONE |
|
|
no contact info
|
ELE13-01456
| ELE-Aging Inspection | 3/3/2016 | 3/3/2016 | 3/3/2016 3:51:17 PM | | DONE |
|
|
too busy
|
ELE16-00670
| Electrical Rough-In | 3/2/2016 | 3/3/2016 | 3/3/2016 3:49:24 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Don Conley r/i ok including new sub feed and sub panel using existing service not damaged in fire
|
ELE15-04011
| Electrical Rough-In | 3/2/2016 | 3/3/2016 | 3/3/2016 3:18:53 PM | P | PASS |
|
|
Contact: Mike Mulvahill, ceiling inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden r/i ok t grid ceilings EXCEPT conference room and governors office
|
ELE16-00506
| Electrical Rough-In | 3/3/2016 | 3/3/2016 | 3/3/2016 2:46:26 PM | P | PASS |
|
|
We are requesting an underground inspection for today in the afternoon. Our contact is Tony @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate r/i underslab raceways from grid line 7 to the south 100% ok to cover
|
ELE16-00580
| Electrical Rough-In | 3/2/2016 | 3/3/2016 | 3/3/2016 2:25:57 PM | P | PASS |
|
|
Under ground inspection on main feeder conduits at garage level. Call Lonny with any questions, thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum r/i ok partial secondaries on north half. Also discuss fire pump again. Waiting for Idaho POwer to ok CT meter mounted directly to ransformer OR ct enclosure mounted inside fire pump room??
|
ELE16-00603
| Final | 3/2/2016 | 3/3/2016 | 3/3/2016 10:50:08 AM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Kelly Felin needed p/s
|
ELE16-00603
| Permanent Service | 3/3/2016 | 3/3/2016 | 3/3/2016 10:49:33 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kelly Felin p/s o/h rec ok
|
ELE16-00406
| Final | 3/2/2016 | 3/3/2016 | 3/3/2016 10:13:28 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk 210.8 (B)(5)-GFCI protection required within 6' of sinks
|
ELE15-03843
| Final | 3/2/2016 | 3/3/2016 | 3/3/2016 9:37:00 AM | A | PASS |
|
|
Mike Phone #: ###-#### corrections made final ok
|
ELE16-00529
| Electrical Rough-In | 3/3/2016 | 3/3/2016 | 3/3/2016 9:02:34 AM | A | PASS |
|
|
Underground in the slab and about grounding new service Phone #: ###-#### Inspection requested via web by Stan Woodward r/i ok underslab raceways and floor boxes. ALSO Stan will install #4 bare copper for concrete encased electrode for new service
|
ELE15-03757
| Electrical Rough-In | 3/1/2016 | 3/3/2016 | 3/3/2016 8:36:49 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mark M r/i OBGYN lobby ceilings ok
|