Inspections for the day of: Tuesday, March 3, 2020.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS18-00472 MIS-Aging Inspection3/3/20203/3/20203/10/2020 10:42:22 AM CANC
BLD13-02186 BLD-Final2/25/20203/3/20203/6/2020 3:30:24 PMPPEND
Mark Phone #: ###-####
BLD19-04072 BLD-Foundation3/2/20203/3/20203/3/2020 4:43:39 PMPNR
Pat Phone #: ###-####
BLD20-00389 BLD-Final3/3/20203/3/20203/3/2020 4:35:45 PMPDONE
Thank you! Phone #: ###-#### Inspection requested via web by Dale Hope,, done and gone
BLD20-00389 DOC - Permit Finaled3/3/20203/3/20203/3/2020 4:22:16 PMPPASS
done.. gone
BLD20-00619 BLD-Footing3/3/20203/3/20203/3/2020 4:21:40 PMPPEND
Brooks Phone #: ###-####// needs hillside approval 1st
BLD19-03056 BLD-Foundation3/3/20203/3/20203/3/2020 4:20:26 PMPPART
Jon Phone #: ###-####// interior slab footings work in progress,,ok
BLD18-03383 BLD-Conference3/3/20203/3/20203/3/2020 4:19:42 PMPPEND
verify status on building/ permit// no one around
BLD18-04407 BLD-Final3/2/20203/3/20203/3/2020 2:53:20 PMPPASS
Need final walkthrough on corrections; window tempered, window opening restrictions and landings for French doors. Thanks! Phone #: ###-#### Inspection requested via web by Beau Brazier// recomended for historic award,, c of c issued
BLD18-04407 DOC - Permit Finaled3/3/20203/3/20203/3/2020 2:51:54 PMPPASS
BLD19-03506 BLD-Conference3/3/20203/3/20203/3/2020 2:20:29 PMPPART
Please call Erik @ 310.755.5987 15 minutes in advance so I can be there.
This is for Framing inspection prior to insulating. Phone #: ###-#### Inspection requested via web by Erik Hagen/// frame walk through,, fire blocking,, joist connections,, header support,, trades,, etc.
BLD20-00670 BLD-Foundation3/2/20203/3/20203/3/2020 1:35:49 PMPPART
stem wall // David Phone #: ###-####// missed a footing point load,, need to get a fix and show the next inspector when the slab footings are called in,, work in progress.. ok to pour stem wall when ready
BLD19-04775 BLD-Framing/Rough-in3/2/20203/3/20203/3/2020 12:51:41 PMAPASS
Jay Walters will be the onsite contact Phone #: ###-#### Inspection requested via web by BRS Permitting// ok per engineer
BLD19-03799 BLD-Conference3/2/20203/3/20203/3/2020 11:41:17 AMAPEND
Phone #: ###-#### Inspection requested via web by John Treat,, will need to go through architect to get fix to leave garage un-finished
MIS20-00043 BLD-Conference2/24/20203/3/20203/3/2020 10:57:24 AMADONE
follow up...// permit has been issued
MIS20-00043 DOC - Permit Finaled3/3/20203/3/20203/3/2020 10:57:07 AMPPASS
permit issued
BLD19-04496 BLD-Conference3/2/20203/3/20203/3/2020 10:56:06 AMAPART
Dave Phone #: ###-#### - Dave called to change time to tomorrow morning,, under floor ok after taping seams and around pony wall footings.. will verify at the final
BLD19-04845 BLD-Footing3/2/20203/3/20203/3/2020 10:37:35 AMAPART
aNDY Phone #: ###-####,, work in progress,, ok
BLD19-03951 BLD-Framing/Rough-in3/2/20203/3/20203/3/2020 10:22:55 AMAPASS
Phone #: ###-#### Inspection requested via web by Ken Litzinger