FIR06-00523
| INSP-Alarm Testing | 3/30/2007 | 3/30/2007 | 3/30/2007 6:00:22 PM | P | DEFR |
|
|
Field inspection performed by M. Timmerman.
|
FIR07-00100
| INSP-Sprinkler Rough-in/Hydro | 3/28/2007 | 3/30/2007 | 3/30/2007 5:58:52 PM | A | DEFR |
|
|
This is just an overhead hydro. Contact is Brian D. @ ###-####. Thank you. Phone #: ###-####
|
FIR06-00591
| INSP-Conference | 3/29/2007 | 3/30/2007 | 3/30/2007 5:58:25 PM | A | DONE |
|
|
Regarding questions for project life safety requirements.
|
FIR07-00194
| INSP-Final Inspection | 3/28/2007 | 3/30/2007 | 3/30/2007 5:55:53 PM | A | PASS |
|
|
Fire alarm permit finaled.
|
FIR06-00101
| INSP-Final Inspection | 3/29/2007 | 3/30/2007 | 3/30/2007 5:55:15 PM | P | FAIL |
|
|
The remainder of building final sprinkler inspection walkthrough completed today, noted heads are overspaced in the linen storage rooms on 2nd and 3rd floors, heads in the electrical room on the 4th floor are overspaced, missing heads at two mechanical closets on the 4th and 3rd floors, need to remove tape covering one head in the pool room, missing ceiling tile at the 1st floor storage rooms.
|
FIR05-00271
| INSP-Final Inspection | 3/29/2007 | 3/30/2007 | 3/30/2007 3:01:21 PM | A | PASS |
|
|
Corrections verified for completion, fire sprinkler passed inspection, permit finaled.
|
FIR06-00558
| INSP-Sprinkler Rough-in | 3/29/2007 | 3/30/2007 | 3/30/2007 2:58:53 PM | A | PART |
|
|
The OH install at the drop ceilings in the hallway adjacent to the OR rooms are approved for cover, one head to be added for complete coverage of the pockets along the corridor as discussed, see plans for areas inspected to date.
|
FIR07-00207
| INSP-Sprinkler Rough-in | 3/29/2007 | 3/30/2007 | 3/30/2007 2:55:28 PM | A | PART |
|
|
Penthouse elevator machine room sprinkler modifications are acceptable, no access available for inspection of the heads at the top and bottom of the shaft.
|
FIR06-00741
| INSP-Alarm Testing | 3/27/2007 | 3/30/2007 | 3/30/2007 2:52:06 PM | A | PART |
|
|
Fire alarm tested satisfactory, room 106A is okay for occupancy, field modifications for the hood FP monitoring points are approved, final pending ceiling tile at room 103 and NFPA 72 forms.
|