Inspections for the day of: Monday, March 30, 2009.
Number of inspections: 9
Percentage of inspections complete: 89 %
Percentage of inspections not complete: 11 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00745 INSP-Conference3/26/20093/27/2009 P 
Inspection follow up.
FIR09-00130 INSP-Final Inspection3/27/20093/30/20093/30/2009 4:37:15 PMPFAIL
No actual alarm testing was performed today but I did a walk through and found strobes overspaced and others blocked by walls, smoke detectors too close to supply air diffusers and the interconnection with the pre-action system had not been pretested and had problems. I marked the deficiency locations on the city approved plans.
FIR08-00778 INSP-Final Inspection3/30/20093/30/20093/30/2009 4:34:43 PMPFAIL
No testing could be completed today due to multiple problems with the pressure switches.
FIR09-00131 INSP-Final Inspection3/30/20093/30/20093/30/2009 2:23:20 PMPPASS
life safety passed.
BLD08-01127 FIRE-Final Inspection3/29/20093/30/20093/30/2009 2:22:21 PMAPASS
Life safety passed.
FIR08-00750 INSP-Final Inspection3/27/20093/30/20093/30/2009 2:21:45 PMAPASS
Permit finaled. The reporting to the central station had to be changed.
BLD09-00340 FIRE-Final Inspection3/30/20093/30/20093/30/2009 12:11:02 PMAFAIL
Provide panic/fire haredware on the two south facing exterior exit doors. Provide panic/fire hardware on the two exit doors from the conference room 103 and provide the correct door swing. These items have been addressed on the city approved plans.
BLD08-02385 FIRE-Final Inspection3/30/20093/30/20093/30/2009 12:07:19 PMAPASS
life safety passed
BLD08-02490 FIRE-Final Inspection3/27/20093/30/20093/30/2009 12:00:38 PMAPASS
life safety passed.