BLD10-02939
| FIRE-Final Inspection | 3/29/2011 | 3/30/2011 | 3/30/2011 4:25:39 PM | P | NR |
|
|
Preliminary life safety inspection completed including UPS and emergency generator tests, noted areas on each floor in need of adjustments in exit signage placement and EM lighting, noted hardware at two doors to be switched, discussed fire extinguishers, building address, occupant load signs, review notes, project schedule, fire alarm work, etc.
|
FIR09-00375
| FIR-Aging Inspection | 3/30/2011 | 3/30/2011 | 3/30/2011 4:18:58 PM | P | PEND |
|
|
Final pending repairs and scheduled retest.
|
FIR11-00087
| INSP-Alarm Testing | 3/30/2011 | 3/30/2011 | 3/30/2011 4:17:48 PM | P | PART |
|
|
Final pending noted corrections.
|
BLD11-00298
| FIRE-Conference | 3/30/2011 | 3/30/2011 | 3/30/2011 4:16:10 PM | P | DONE |
|
|
Regarding fire sprinkler coverage at the electrical closet.
|
BLD10-01853
| FIRE-Sprinkler Rough-in | 3/30/2011 | 3/30/2011 | 3/30/2011 4:14:52 PM | A | PART |
|
|
Supply line flush okayed
|
FIR11-00023
| INSP-Sprinkler Rough-in | 3/30/2011 | 3/30/2011 | 3/30/2011 4:13:47 PM | A | PART |
|
|
Work to date okayed for cover.
|
FIR11-00086
| INSP-Sprinkler Rough-in/Hydro | 3/30/2011 | 3/30/2011 | 3/30/2011 4:10:10 PM | A | PART |
|
|
|
BLD11-00306
| FIRE-Sprinkler Rough-in | 3/30/2011 | 3/30/2011 | 3/30/2011 4:08:33 PM | A | PART |
|
|
Ref. FIR11-00136
|