BLD15-00881
| FIRE-Final Inspection | 3/30/2015 | 3/30/2015 | 3/31/2015 7:55:26 AM | P | PASS |
|
|
Life safety passed. Provide address before building inspection and per plan review the emergency lighting is not required.
|
FIR14-00894
| INSP-Sprinkler Rough-in | 3/27/2015 | 3/30/2015 | 3/30/2015 3:25:14 PM | A | PASS |
|
|
See the city approved plans for piping that is ok to cover above hard lids.
|
FIR15-00161
| INSP-Final Inspection | 3/26/2015 | 3/30/2015 | 3/30/2015 12:07:54 PM | A | PASS |
|
|
Permit finaled
|
FIR15-00096
| INSP-Sprinkler Rough-in | 3/27/2015 | 3/30/2015 | 3/30/2015 10:34:04 AM | A | PART |
|
|
Inspection was for east wing of the 2nd floor. See the city approved plans for locations marked in red and dated with todays date. I noted one overspaced head that can be verified at final and two locations where the cpvc piping may be exceeding maximum flex. Many dummy drops are installed and no actual rc's or pendants and in these locations the dummy drop is very close to a wall.Rooms are ok to cover as marked (noted above). I spoke to the General Contractor about the fire stopping in the vertical chases and needing access to verifiy the fire stopping. He is going to try for a variance due to the fact he is building the vertical chases to meet 2 Hour construction.
|
BLD15-00825
| FIRE-Final Inspection | 3/27/2015 | 3/30/2015 | 3/30/2015 10:10:35 AM | A | PASS |
|
|
life safety passed
|