BLD16-02888
| BLD-Aging Inspection | 3/30/2017 | 3/30/2017 | 4/3/2017 6:43:04 AM | | CANC |
|
|
|
BLD16-03182
| BLD-Aging Inspection | 3/30/2017 | 3/30/2017 | 4/3/2017 6:42:39 AM | | CANC |
|
|
|
BLD16-03359
| BLD-Final | 3/29/2017 | 3/30/2017 | 4/3/2017 6:42:07 AM | P | PART |
|
|
Building 10 // Terry Phone #: ###-#### ok for temp
|
BLD16-03703
| BLD-Final | 3/30/2017 | 3/30/2017 | 3/31/2017 9:53:05 AM | P | PART |
|
|
ok for temp occ needs to fix ada restroom
|
BLD16-00172
| BLD-Final | 3/29/2017 | 3/30/2017 | 3/31/2017 6:12:51 AM | P | PART |
|
|
Building Final for Dave to verify safety railing is in-place at 2nd Floor Phone #: ###-#### Inspection requested via web by Joel Halfhill ok for temp occ of second and fourth floors
|
BLD15-04468
| BLD-Final | 3/30/2017 | 3/30/2017 | 3/31/2017 6:11:00 AM | A | PART |
|
|
Final walk am attempt. Call Adam. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for T.C.O.
|
BLD16-04303
| BLD-Framing/Rough-in | 3/30/2017 | 3/30/2017 | 3/30/2017 5:05:16 PM | P | PASS |
|
|
Plans and engineering on site at furnace platform Inspection requested via web by Erby Gonzales
|
BLD17-00770
| BLD-Final | 3/30/2017 | 3/30/2017 | 3/30/2017 2:30:33 PM | P | PASS |
|
|
Brian Phone #: ###-####
|
BLD17-00579
| BLD-Foundation | 3/29/2017 | 3/30/2017 | 3/30/2017 1:44:51 PM | A | CANC |
|
|
Late morning // Greg Phone #: ###-####
|
BLD16-03292
| BLD-Foundation | 3/28/2017 | 3/30/2017 | 3/30/2017 1:43:41 PM | A | PEND |
|
|
Robert Phone #: ###-####
|
BLD16-04581
| BLD-Framing/Rough-in | 3/29/2017 | 3/30/2017 | 3/30/2017 1:43:15 PM | A | CANC |
|
|
would like call ahead Phone #: ###-####
|
BLD16-02987
| BLD-Framing/Rough-in | 3/27/2017 | 3/30/2017 | 3/30/2017 10:25:46 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD16-03468
| BLD-Final | 3/29/2017 | 3/30/2017 | 3/30/2017 10:04:27 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD16-03468
| DOC - Permit Finaled | 3/30/2017 | 3/30/2017 | 3/30/2017 10:04:16 AM | P | PASS |
|
|
|
BLD17-00597
| BLD-Framing/Rough-in | 3/29/2017 | 3/30/2017 | 3/30/2017 9:53:05 AM | A | PASS |
|
|
Dave Phone #: ###-####
|
BLD17-00098
| BLD-Wall Bracing | 3/29/2017 | 3/30/2017 | 3/30/2017 9:32:57 AM | A | PASS |
|
|
Carlos Phone #: ###-####
|
BLD16-03359
| BLD-Framing/Rough-in | 3/29/2017 | 3/30/2017 | 3/30/2017 9:20:36 AM | A | PASS |
|
|
Building 6 and 10 // Terry Phone #: ###-####
|
BLD17-00664
| BLD-Framing/Rough-in | 3/29/2017 | 3/30/2017 | 3/30/2017 9:05:06 AM | A | PEND |
|
|
Lynn Phone #: ###-#### framing ok but needs elec done
|
BLD16-04154
| BLD-Foundation | 3/29/2017 | 3/30/2017 | 3/30/2017 8:53:22 AM | A | CANC |
|
|
Jared Phone #: ###-####
|
BLD16-04480
| BLD-Foundation | 3/29/2017 | 3/30/2017 | 3/30/2017 8:51:57 AM | A | CANC |
|
|
The pour is scheduled for 9 am. MTI will be present for a rebar inspection. Phone #: ###-#### Inspection requested via web by Nicholas Miller
|