ELE13-02849
| Electrical Rough-In | 3/31/2014 | 3/31/2014 | 3/31/2014 2:22:18 PM | P | PASS |
|
|
Ceiling inspection. Contact is Alan Krishnek Phone #: ###-#### >> Inspection requested via web by Scott Campbell rough-in ok cover ceiling grid in areas A and B
|
ELE14-00741
| Electrical Rough-In | 3/29/2014 | 3/31/2014 | 3/31/2014 1:45:51 PM | P | PASS |
|
|
Cover inspection for garage walls. Thank you! Phone #: ###-#### >> Inspection requested via web by Adam Staigle Rough-in ok cover garage
|
ELE14-00759
| Electrical Rough-In | 3/28/2014 | 3/31/2014 | 3/31/2014 1:33:09 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Harvey Reyna rough-in ok cover walls
|
ELE14-00742
| Electrical Rough-In | 3/31/2014 | 3/31/2014 | 3/31/2014 1:09:38 PM | P | PASS |
|
|
early as poss // trench // JR (father) Phone #: ###-#### rough-in ok cover trench house to shop
|
ELE14-00769
| Final | 3/31/2014 | 3/31/2014 | 3/31/2014 12:56:44 PM | P | PASS |
|
|
Thanks !!!, Dan ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Mitchell job complete, final ok
|
ELE14-00769
| Electrical Rough-In | 3/31/2014 | 3/31/2014 | 3/31/2014 12:56:00 PM | P | PASS |
|
|
Thanks !!!, Dan ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Mitchell UL listed control panel rough-in ok
|
ELE14-00584
| Electrical Rough-In | 3/28/2014 | 3/31/2014 | 3/31/2014 9:30:37 AM | A | PASS |
|
|
30 minute call ahead if possible please as electrician is not on site. Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton rough-in ok cover ceiling grid
|
ELE14-00584
| Permanent Service | 3/31/2014 | 3/31/2014 | 3/31/2014 9:21:04 AM | A | PASS |
|
|
30 minute call ahead if possible please as electrician is not on site. Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton p/s u/g n ok meter pac
|
ELE14-00414
| Final | 3/28/2014 | 3/31/2014 | 3/31/2014 9:07:06 AM | A | PASS |
|
|
We are requesting a final inspection for Monday 3/31/14 in the AM. Our onsite contact is Rod @ ###-####. Thank you. Phone #: ###-#### >> Inspection requested via web by Clint Tate Phase one final ok
|
ELE14-00537
| Electrical Rough-In | 3/28/2014 | 3/31/2014 | 3/31/2014 8:40:10 AM | A | FAIL |
|
|
The garage code is xxxxx. Please let me know if there are any problems. Thanks Phone #: ###-#### >> Inspection requested via web by Clay Morgan Framing not completed for all electrical installations, hall bathroom, two gang switch box in cold air return
|
ELE14-00584
| Electrical Rough-In | 3/28/2014 | 3/31/2014 | 3/28/2014 3:08:32 PM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton Inspection cancelled from web by: Kerri Hamilton
|