Inspections for the day of: Monday, March 31, 2014.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-01159 Site Preparation3/28/20143/31/20143/31/2014 3:38:46 PMPPASS
3:00 PM - new subdivision development. BMPs should be installed. Trilogy Development Sean : ###-####



Inspection report:

Attendees: John Laude (RP) and Sean from Trilogy
Contractor: Nampa Paving

1. Construction of roads and sewer for phase 1 is scheduled to begin this week. The entire area listed on permit will not be included in this phase. Silt fence BMP protects the 8 mile creek channel adjacent to site along phase I. No dewatering, on or off-hauling of dirt is expected.

2. Construction entrance will be built once road is cut, I agreed to allow unless track out becomes an issue.

3. DIs to catch basins on Hollandale have filter bag protection.

4. Existings stormwater swales will be modified and are therefore not surrounded by wattles. Currently they will serve as sediment traps.

Approved for construction.
ESC13-00749 General Inspection3/31/20143/31/20143/31/2014 11:27:38 AM PASS
Roofing in progress. Contractors parking on street. No corrections required at this time.
ESC14-00109 Random Inspection3/31/20143/31/20143/31/2014 11:22:07 AMAPASS
Culvert for Pennitentiary Canal has been installed. Site used an Outpak washout and contained slurry as directed. Disturbed ground is not stabilized. No significant trackout to Warm Springs. Will check to see when next phase of project is scheduled.
ESC13-00755 Tracking Control3/31/20143/31/20143/31/2014 11:10:47 AMAPART
Follow up inspection from CN issued Friday 3/28
.
Correction complete: Construction entrances were rebuilt and roads were swept and are in better condition than last Friday.

Corrections remaining:
1. Trackout still visible on all roads accessing site, need to increase sweeping or use different sweeping vehicle.
2. No wheel washing observed, unclear if wheel wash area situation was changed - were washing on top of construction entrance creating more mud.
ESC13-00069 General Inspection3/31/20143/31/20143/31/2014 10:58:15 AM PASS
Terraces underground garage. Some track out on roads from site. CN posted under main site permit ESC13 -00755. See activites for details.
ESC13-00199 General Inspection3/31/20143/31/20143/31/2014 10:48:23 AM PASS
This permit covers Block 36 and majority of house are permitted through Tahoe Homes. Streets, sidewalks, and gutters are clean. Stormwater catch basins have DI protection.

Approved.
ESC12-01032 General Inspection3/31/20143/31/20143/31/2014 10:24:20 AM PASS
No sediment leaving site, Permit posted, no exterior work observed. No activity on BLD permit since Sept 2013. May close next inspection.
ESC13-00768 General Inspection3/31/20143/31/20143/31/2014 9:05:13 AM PASS
Related to BLD14-00087. Original BLD was voided. WIP. No violations.
ESC12-00344 Aging Inspection3/31/20143/31/20143/31/2014 8:32:39 AM PASS
Finaled.
ESC12-00344 DOC - Permit Finaled3/31/20143/31/20143/31/2014 8:32:23 AMPPASS
All earthwork has been stabilized. No materials related to project remaining onsite. ESC conditions satisfied; BLD permit is finaled.