BLD1054510
| INSP - Final | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | A | NR |
|
|
NEED TAWNEY'S OK FOR SPRINKLERS
|
BLD1054682
| INSP - Final | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | A | NR |
|
|
NEED MECH. OK, TOLD BASHFORD TO CALL ALAN H.
|
BLD97-02259
| INSP - Framing/Rough-in | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | A | NR |
|
|
REC'D NON-COMPLYING REPORT ON DOORS FROM INTER-TEK (WARNOCK-HERSEY)...CALLED JOEL BROWN, WAITING FOR REPLY.
|
BLD97-03694
| INSP - Foundation | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | A | PASS |
|
|
BAR IN PLACE; TOLD CONT TO HAVE ALL MASONRY INSPS CALLED IN...NO SPEC. INSP. PER ARLAN S.
|
BLD98-00003
| INSP - Foundation | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | A | NR |
|
|
NOT FDN INSP, DISCUSSED PLAN & FDN REQ'S W/ BRIAN OF STATEWIDE
|
BLD98-00275
| INSP - Foundation | 3/3/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | A | PART |
|
|
FOOTING--MIKE PAGER ####-####--POURING AT 7:30 FTG POURED, NO PLANS OR HUMANS ONSITE....
|
BLD98-00275
| INSP - Foundation | 3/3/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | A | NR |
|
|
Mike Herrick - ###-#### - footings FTGS DONE, NO FND WALL FORMED; NEED HOLD DOWNS & MODIFICATION PER PLANS
|
BLD97-01848
| INSP - Framing/Rough-in | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | P | PART |
|
|
SUSPENDED PARTITION AT DELI OK PER RESUB DETAIL...NEED TO INSP HOOD SHAFT, WORK NOT DONE THAT AREA.
|
MEC98-00733
| INSP - Framing/ Rough-in | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | P | PART |
|
|
###-#### carol...GAS TEST OK, C/N ON ASTRO-FOIL IN PLENUMS
|
BLD97-02911
| INSP - Framing/Rough-in | 3/4/1998 | 3/4/1998 | 3/4/1998 12:00:00 AM | P | PART |
|
|
"HALL" AREA, NEW HEADERS, ETC OK TO FILL IN TO MATCH EXISTING WALL. 1/2" TYPE X OK
|
BLD97-02729
| INSP - Final | 3/5/1998 | 3/4/1998 | 3/4/1997 12:00:00 AM | P | FAIL |
|
|
OK FOR T/O, TAWNEY SIGNED KEEP STRUCT C/N, CARD TO OWNER NEED CHK GRID WIRES,WILL RECALL
|