Inspections for the day of: Thursday, March 4, 2004.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRick Jackson
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR03-00690 FIR-Aging Inspection3/4/20043/4/20043/4/2004 12:00:00 AM PASS
Per Ken this is phased work that is scheduled for completion by 12/04. The first floor is in progress and the head end is completed. There is an agreement with BFD for the phasing. 3/4/2004 9:54:48 AM
FIR04-00030 INSP-Final Inspection3/3/20043/4/20043/4/2004 12:00:00 AMAPASS
George ; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD03-02641 FIRE-Final Inspection3/4/20043/4/20043/4/2004 12:00:00 AMAPASS
will have occupant load sign at main exit for structural inspector 3/4/2004 11:25:25 AM
BLD03-02641 FIRE-Final Inspection3/4/20043/4/20043/4/2004 12:00:00 AMAPASS
will have occupant load sign at main exit for structural inspector 3/4/2004 11:25:25 AM
FIR04-00062 INSP-Final Inspection3/4/20043/4/20043/4/2004 12:00:00 AMPFAIL
this is robs cell could we please schedule it for after 2:30 pm; Phone #: ###-#### Internet Inspection Request from: Terry Owsley Strobes not sync'd; need to test voltage drops and current draw on NAC's 3/4/2004 5:06:05 PM
MIS04-00058 FIR-Final3/3/20043/4/20043/4/2004 12:00:00 AMPPART
jerry; Phone #: ###-#### Internet Inspection Request from: Annette Moore needs extinguisher and sign above doors 3/4/2004 1:31:44 PM
FIR03-00777 INSP-Final Inspection3/4/20043/4/20043/4/2004 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 3/4/2004 at 8:42:11 AM. Contact: ###-####.
FIR03-00593 INSP-Final Inspection3/4/20043/4/20043/4/2004 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 3/4/2004 at 8:43:32 AM. Contact: ###-####.