Inspections for the day of: Monday, March 5, 2007.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-02994 FIRE-Final Inspection3/5/20073/5/20073/6/2007 10:27:48 AMPPASS
Fire life safety finaled.
FIR06-00967 INSP-Final Inspection3/2/20073/5/20073/6/2007 10:26:50 AMPPASS
Strobe sync repaired while on site, fire alarm final field inspection passed.
FIR07-00064 INSP-Final Inspection3/1/20073/5/20073/6/2007 10:24:21 AMACANC
Cancel inspection per phone call from contractor.
FIR06-00583 FIR-Aging Inspection3/5/20073/5/20073/5/2007 2:09:41 PM DONE
Work in progress.
FIR06-00844 INSP-Sprinkler Rough-in3/5/20073/5/20073/5/2007 2:07:55 PMPPART
UG fire supply line and remote FDC UG piping are good for cover from the point of connection at the street to just prior to the last 90 at the building, will need to verifiy last piece of 4" FDC piping, link seals, and thrust blocking at the 90's which are not yet completed at this time.
FIR06-00893 INSP-Final Inspection3/2/20073/5/20073/5/2007 12:55:24 PMAPASS
Corrections field verified for compliance, final inspection passed, permit finaled.
FIR07-00162 INSP-Sprinkler Rough-in3/2/20073/5/20073/5/2007 11:55:16 AMAPART
Fire sprinker modifications for room #3 are satisfactory, no access to room #4 at this time due to flooring installation.
FIR07-00086 INSP-Sprinkler Rough-in3/2/20073/5/20073/5/2007 11:53:16 AMAPART
Fire sprinkler install at the north portion of the remodel as noted on approved plan set is okay for cover.
FIR06-00558 INSP-Sprinkler Rough-in3/2/20073/5/20073/5/2007 11:51:41 AMAPART
OH fire sprinkler rough-in as noted on approved plan set is acceptable for cover, c/n items from previous inspection of this area are complete.
BLD06-03462 FIRE-Final Inspection3/3/20073/5/20073/5/2007 11:08:02 AMAPASS
Fire life safety inspection passed, noted the provided PFE to be lowered to no higher than 48" AFF prior to structural final as agreed.