FIR14-00047
| INSP-Final Inspection | 3/4/2014 | 3/5/2014 | 3/5/2014 4:28:10 PM | P | PART |
|
|
Final pending coverage below two overhead garage doors. Add sprinkler protection or reduce obstruction to meet NFPA 13.
|
BLD14-00479
| FIRE-Final Inspection | 3/5/2014 | 3/5/2014 | 3/5/2014 4:21:28 PM | P | PASS |
|
|
Life safety inspection completed satisfactory per conditions of the issued permit documents.
|
FIR13-00693
| INSP-Sprinkler Rough-in | 3/4/2014 | 3/5/2014 | 3/5/2014 12:38:14 PM | A | PART |
|
|
Remainder of overhead work at the grid ceilings completed. Okayed for cover.
|
FIR14-00119
| INSP-Sprinkler Rough-in | 3/4/2014 | 3/5/2014 | 3/5/2014 12:34:55 PM | A | PART |
|
|
Overhead rough-in including new main and branchlines approved for cover at the grid ceilings.
|
FIR14-00118
| INSP-Sprinkler Rough-in | 3/4/2014 | 3/5/2014 | 3/5/2014 11:28:28 AM | A | PART |
|
|
Inspection for UG fire supply line completed at five exposed locations. Okayed for cover.
|
FIR13-00558
| INSP-Sprinkler Rough-in | 3/5/2014 | 3/5/2014 | 3/5/2014 10:32:28 AM | A | PART |
|
|
Overhead work at the grid ceiling areas approved for cover.
|
BLD12-01528
| FIRE-Final Inspection | 3/4/2014 | 3/5/2014 | 3/5/2014 9:55:34 AM | A | FAIL |
|
|
Missing two exit signs, one EM light per plan sheet E3.0. Need to provide revised floorplan due to field changes.
|