MEC02-00646
| Pressure Test | 3/5/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | A | PASS |
|
|
A-1 FIREPLACE ###-####
|
MEC02-00646
| Final | 3/5/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | A | PASS |
|
|
A-1 FIREPLACE ###-####
|
BLD01-01109
| BLD-Other | 3/5/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/05/2002 at 11:49:08. Contact: ###-####. ceiling grid in new nurses station 3/6/2002 1:00:00 PM
|
BLD02-00178
| BLD-Framing/Rough-in | 3/5/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | A | PART |
|
|
###-#### shear ok needs elec r/i and seal package 3/6/2002 11:36:35 AM
|
BLD02-00319
| BLD-Framing/Rough-in | 3/5/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/05/2002 at 16:48:43. Contact: ###-####.
|
BLD01-03126
| BLD-Final | 3/6/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | P | PASS |
|
|
###-#### ok for perm occ 3/6/2002 5:03:53 PM
|
BLD02-00277
| BLD-Final | 3/6/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | P | PASS |
|
|
###-#### PAUL
|
BLD01-01188
| BLD-Final | 3/6/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | P | FAIL |
|
|
fn -travis -###-#### org c/n not completed 3/6/2002 2:38:25 PM
|
BLD01-01189
| BLD-Final | 3/6/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | P | FAIL |
|
|
###-####- travis re-insp c/n on site 3/6/2002 2:37:38 PM
|
MEC01-03052
| Final | 3/6/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 425 On 3/6/2002 1:45:40 PM
|
BLD02-00028
| BLD-Final | 3/5/2002 | 3/6/2002 | 3/6/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/05/2002 at 14:39:47. Contact: ###-####.
|