MEC18-01040
| Final | 3/6/2018 | 3/6/2018 | 3/6/2018 4:00:58 PM | P | PASS |
|
|
Ready around 3-ish. Call on way. Craig ###-####. Phone #: ###-#### Inspection requested via web by Krista Boss- AC coil CO ok
|
MEC18-00847
| Rough-in | 3/5/2018 | 3/6/2018 | 3/6/2018 3:29:06 PM | P | NR |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- still installing
|
MEC18-00847
| Pressure Test | 3/5/2018 | 3/6/2018 | 3/6/2018 3:28:37 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- 20lb gas pass
|
MEC18-00916
| Rough-in | 3/5/2018 | 3/6/2018 | 3/6/2018 3:14:44 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- R/I ok- will pass when gas holds pressure
|
MEC18-00916
| Pressure Test | 3/5/2018 | 3/6/2018 | 3/6/2018 3:14:13 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- gauge at 10psi
|
MEC18-00956
| Rough-in | 3/5/2018 | 3/6/2018 | 3/6/2018 2:44:53 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- R/I ok- Fireplace R/I ok
|
MEC18-00918
| Final | 3/6/2018 | 3/6/2018 | 3/6/2018 2:17:40 PM | P | PASS |
|
|
Please call Douglas Scheffer at ###-#### about 15 minutes prior to inspection so he can get home from work. Phone #: ###-#### Inspection requested via web by Mary LaFayette- furnace gas piping CO ok
|
MEC18-00826
| Final | 3/5/2018 | 3/6/2018 | 3/6/2018 1:27:59 PM | P | PASS |
|
|
Please call Tyler when on way at ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- routing of new duct off existing unit ok- exposed duct with transfer register-all good
|
MEC18-00826
| Card not on site to sign | 3/6/2018 | 3/6/2018 | 3/6/2018 1:27:05 PM | P | PASS |
|
|
Please call Tyler when on way at ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- no card to sign onsite
|
MEC17-02534
| Final | 3/5/2018 | 3/6/2018 | 3/6/2018 11:24:06 AM | A | PART |
|
|
Please call Brad ###-####, Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum- need airbalance report for kitchen equipment
|
MEC18-00776
| Rough-in | 3/6/2018 | 3/6/2018 | 3/6/2018 10:51:24 AM | A | PASS |
|
|
F/P R/I ok
|
MEC18-00773
| Rough-in | 3/5/2018 | 3/6/2018 | 3/6/2018 10:50:40 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ashley Stegemann- f/p R/I ok
|
MEC18-00861
| Final | 3/2/2018 | 3/6/2018 | 3/6/2018 10:31:42 AM | A | PASS |
|
|
Please call homeowner 30 minutes in advance for access, if the answering machine comes on please start talking and she will answer, please call Ryan with any questions ###-####. - Thank you! Phone #: ###-#### Inspection requested via web by Lea Briggs- furnace CO ok
|
MEC18-01039
| Final | 3/5/2018 | 3/6/2018 | 3/6/2018 10:03:18 AM | A | PASS |
|
|
Please call Dave at ###-#### or Dan at ###-#### with a 30 minute heads up arrival time. Tenant also states "they will be home"....... Thanks! Phone #: ###-#### Inspection requested via web by David or K Cole- furnace in crawl CO ok
|
MEC18-00993
| Pressure Test | 3/5/2018 | 3/6/2018 | 3/6/2018 9:38:07 AM | A | FAIL |
|
|
customer needs to leave the home by1230 so if it is possible to do the test before then that would be great. Customers name is Sheela and her # is above.
Thanks! Phone #: ###-#### Inspection requested via web by Marisa Hone- guage at 0psi
|
MEC18-00889
| Final | 3/6/2018 | 3/6/2018 | 3/6/2018 9:21:44 AM | A | PASS |
|
|
Mantel CO gas piping ok
|
MEC18-00889
| Rough-in | 3/5/2018 | 3/6/2018 | 3/6/2018 9:20:49 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mike Almanza- fireplace R/I ok- co installed
|
MEC18-00889
| Pressure Test | 3/5/2018 | 3/6/2018 | 3/6/2018 9:20:22 AM | A | PASS |
|
|
THE EARLIER THE BETTER FOR EVERYONE INVOLVED. NEED INSPECTION BEFORE WE CAN PROCEED WITH INSTALL. PLEASE CALL ANN OR PAT @ ###-#### OR ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza- 20lb gas pass
|
MEC18-00287
| Final | 3/6/2018 | 3/6/2018 | 3/6/2018 9:02:32 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by dannyel chaloupka Inspection cancelled from web by: dannyel chaloupka
|
MEC18-00960
| Final | 3/5/2018 | 3/6/2018 | 3/6/2018 8:41:07 AM | A | PASS |
|
|
845-900am- furnace heat pump ok
|
MEC17-02877
| Mec-Aging Inspection | 3/6/2018 | 3/6/2018 | 3/6/2018 8:29:27 AM | | PEND |
|
|
contractor will reschedule final per phone call
|
MEC17-01575
| Mec-Aging Inspection | 3/6/2018 | 3/6/2018 | 3/6/2018 8:26:46 AM | | PEND |
|
|
contractor to schedule final per phone call
|
MEC16-04791
| Conference | 3/5/2018 | 3/6/2018 | 3/6/2018 8:24:24 AM | A | PASS |
|
|
###-####- 815am
|
MEC16-04791
| Final | 3/6/2018 | 3/6/2018 | 3/6/2018 8:24:10 AM | A | PASS |
|
|
###-####- 815am- electric furnace heat pump ok
|
MEC18-01020
| Pressure Test | 3/5/2018 | 3/6/2018 | 3/5/2018 3:00:41 PM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Devony Bullard Inspection cancelled from web by: Devony Bullard
|
MEC18-01020
| Pressure Test | 3/5/2018 | 3/6/2018 | 3/5/2018 2:58:47 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Devony Bullard Inspection cancelled from web by: Devony Bullard
|
MEC18-01020
| Rough-in | 3/5/2018 | 3/6/2018 | 3/5/2018 2:58:45 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Devony Bullard Inspection cancelled from web by: Devony Bullard
|
MEC18-01022
| Pressure Test | 3/5/2018 | 3/6/2018 | 3/5/2018 2:58:39 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Devony Bullard Inspection cancelled from web by: Devony Bullard
|
MEC18-01022
| Rough-in | 3/5/2018 | 3/6/2018 | 3/5/2018 2:58:37 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Devony Bullard Inspection cancelled from web by: Devony Bullard
|
MEC18-01022
| Final | 3/5/2018 | 3/6/2018 | 3/5/2018 11:48:49 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Devony Bullard Inspection cancelled from web by: Devony Bullard
|