BLD20-00671
| BLD-Other | 3/6/2020 | 3/6/2020 | 3/6/2020 4:20:05 PM | P | DONE |
|
|
Inspection on this completed project. We replaced two small slopes on the front of the roof, removed a decorative gable that was installed improperly and causing leaks, and replaced a couple sheets of decking. Phone #: ###-#### Inspection requested via web by Michael La Pointe
|
BLD20-00671
| DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 4:19:54 PM | P | PASS |
|
|
|
BLD19-02939
| BLD-Framing/Rough-in | 3/6/2020 | 3/6/2020 | 3/6/2020 3:37:34 PM | P | PASS |
|
|
armando Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD18-04520
| BLD-Energy code compliance | 3/6/2020 | 3/6/2020 | 3/6/2020 2:58:33 PM | P | PASS |
|
|
chris Phone #: ###-####. Gyp added behind ADA tub and blocking added.
|
BLD19-02464
| BLD-Framing/Rough-in | 3/6/2020 | 3/6/2020 | 3/6/2020 2:28:37 PM | P | PART |
|
|
Ed Phone #: ###-####. @hr. shaft for elevator. Need to verify type of sheet rock being used. GA file notes 1/2" type C, contractor has used 5/8 type X.
|
BLD19-04713
| BLD-Final | 3/6/2020 | 3/6/2020 | 3/6/2020 1:11:38 PM | P | FAIL |
|
|
aNGELA Phone #: ###-####. Provide smoke detectors in bedrooms and combo upstairs.
|
BLD18-01027
| BLD-Conference | 3/5/2020 | 3/6/2020 | 3/6/2020 11:27:59 AM | A | FAIL |
|
|
Ken Phone #: ###-####. Level 2 framing from grid 8W going west has been covered. Contractor to remove sheetrock around columns and at 10 random locations were there are floor penetrations to ensure firestopping has been completed.
|
BLD19-03969
| BLD-Framing/Rough-in | 3/5/2020 | 3/6/2020 | 3/6/2020 10:43:44 AM | A | PART |
|
|
Jason Phone #: ###-####. Interior steel stud framed walls and soffits in open office area phase 1. Needs electrical rough in inspection. Also needs to add missing screws in framing.
|
BLD20-00468
| BLD-Wall cover | 3/5/2020 | 3/6/2020 | 3/6/2020 10:05:17 AM | A | PASS |
|
|
Phone #: 2086081784 >> Inspection requested via mobile web by Bud Lockhart . Missing kickers at top of wall have been installed.
|
BLD20-00055
| BLD-Wall Bracing | 3/5/2020 | 3/6/2020 | 3/6/2020 9:50:03 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD20-00049
| BLD-Energy code compliance | 3/4/2020 | 3/6/2020 | 3/6/2020 9:22:51 AM | A | PASS |
|
|
Inspection requested via web by Rob Ashworth
|
BLD19-04907
| BLD-Framing/Rough-in | 3/4/2020 | 3/6/2020 | 3/6/2020 9:07:29 AM | A | PASS |
|
|
Julian Phone #: ###-####. Interior steel stud framed walls for closet.
|
BLD19-02949
| BLD-Ceiling Grid Inspection | 3/5/2020 | 3/6/2020 | 3/6/2020 8:51:53 AM | A | PASS |
|
|
Gene Phone #: ###-####
|
MIS20-00074
| BLD-Conference | 3/3/2020 | 3/6/2020 | 3/6/2020 8:23:55 AM | A | PASS |
|
|
Check on status...
|
MIS20-00074
| DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 8:23:43 AM | P | PASS |
|
|
Per the homeowner, no remodel or new construction work in basement has taken place. Needs to resolve electrical permit. Home owner stated he is renting the basement. Advised homeowner to talk with zoning.
|