FIR05-00425
| INSP-Sprinkler Rough-in/Hydro | 3/6/2006 | 3/7/2006 | 3/8/2006 11:05:23 AM | P | FAIL |
|
|
Items lacking for pump test approval include verification of flow test performance curve data, jockey pump controller repair, all items required per NFPA 20 for acceptance testing including a pump mfg. representative who shall be present for the field test (NFPA 20 2003 14.2.1).
|
FIR05-00425
| INSP-Sprinkler Rough-in/Hydro | 3/3/2006 | 3/7/2006 | 3/7/2006 3:22:07 PM | A | PART |
|
|
Witnessed trip test functionality only (no alarm) of the 2nd and 1st floor dry systems, the air pressure may need to be adjusted per recommendation in manufacturer data sheets, the automatic air compressors must meet requirements of NFPA 13 7.2.6.6.
|
BLD05-03152
| FIRE-Final Inspection | 3/6/2006 | 3/7/2006 | 3/7/2006 3:07:26 PM | P | FAIL |
|
|
Provide approved hardware at the pocket door per review note #6, post max occ. load sign with the correct number, need to inspect patio gate hardware when installed, knox box cannot be located behind the patio enclosure, the fire extinguisher must be 48" AFF max.
|
FIR05-00404
| INSP-Sprinkler Rough-in/Hydro | 3/6/2006 | 3/7/2006 | 3/7/2006 12:53:04 PM | A | PART |
|
|
Overhead hydrostatic test passed.
|